1. How does the role of a CA differ to that of an EA?
a. The role of a CA differs to that of an EA as the CA simply administers the contract. The EA is responsible for all duties that the employer would usually perform.
b. The CA is impartial.
a. 50% retention is released (subject to the contract)
b. The 12 months defects period starts.
c. The ability to impose Liquidated Damages is ceased.
a. On the Data centre procurement project, I negotiated the inclusion of items and the rates with the vendor, basing their costs on framework rates, and previous recent project submissions. I undertook critical analysis of the inclusion of items, ensuring substantiation and backup was received, as well as engineer approval where required.
b. I deem a negotiation successful when I can prove and substantiate to my client that there is value for money being achieved in the costs, and that they are in lie with current market rates. I also deem I t a success when successful clarification has been achieved between parties.
a. PM in NEC
b. QS isn’t in NEC.
c. NEC collaborative
d. JCT has legal jargon, NEC is easier wording.
e. NEC more expensive to administer, more paperwork.
a. A performance bond is issued to one party of a contract as a guarantee against the failure of the other party to meet obligations in the contract.
a. Where the client needs to reduce the risk of non-performance of the contractor
b. Where the contractor doesn’t have a parent company.
c. If the contractor is new to working with this client.
d. If there is an ongoing economic crisis
a. On demand – payable immediately on beneficiary’s demand
b. Conditional – requires certain conditions to be met.
a. I would advise that this falls outside my area of expertise and knowledge, and I am not able to advise on this. I would suggest the client seek internal advice and legal help on this, to calculate what they would be owed. I would assist the client in noting any considerations that need to be made in relation to what costs may need to be sought after.
a. Sectional completion is PC of a section of works, each section will have completion dates and rates of LAD’s, sectional completion is also in the contract, whereas partial possession is not pre agreed or stipulated in the contract.
a. At the minute this is more common in the present market
b. I would firstly be concerned the contractor cannot provide this, as it could be proof that their financial situation is not good, I would therefore advise the client that entering into a contract with this contractor could be a large risk, which could be mitigated by diligent financial checks, such as Dunn and Bradstreet.
a. Usually, the value is 10% of the contract sum, and cost is 1%.
a. There is no current fixed date for completing works.
b. Usually this is down to the CA not doing his job properly.
a. Contractor can claim loss and expense due to Employers’ error.
a. They entitle the contractor to claim loss and expense.
a. Variations
b. Instructions
c. Impediment by the Employer
a. Entitles the Contractor to an EoT
a. Deferment of Possession
b. Variations
c. Impediment by the Employer
d. Exceptionally adverse weather conditions
e. In the new JCT suite – Covid-19/global pandemics
f. Force majeure
a. Act of God.
a. There are no clear rules on this, each case has to be judged separately, and identify all causes and effects.
a. Contains statutory provisions relating to all projects over 45 days
a. It is an amount deducted from payment to the contractor and retained until PC and EoMGD, it provides an incentive for the contractor to come and complete the works
a. Retention bond, this is provided by the contractor for the same value, and is used to aid the contractors cashflow.
a. Then additional retention is deducted on that amount.