18. How would you go about re tendering.
a. I would first create a shortlist of contractors by issuing out expressions of interest and getting feedback, with the hopes of having between 3-4 tenderers. I would then issue the tender information, in this case as soon as possible, ensuring that they all had the same times, and sufficient time, in which to price the works.
a. A negotiated procurement route was chosen because the clients priority was speed to start construction, it was also with a trusted contractor that the client preferred, this allowed earlier onboarding of the contractor to the project.
a. Previous satisfactory work carried out by contractor and myself, locality to the region, experience delivering similar schemes
a. As the client wanted to retain control over the architectural design elements, but also wanted a standard contract for medium and regular sized construction projects, that are straightforward in nature, it contained all of the relevant clauses.
a. There was a risk that the contractor could take advantage of being the only tendering contractor and price this into the tender return. Therefore, this was mitigated by the contractor providing 3 quotes on all major packages. quotes were also interrogated in detail, and large measured items cross checked and remeasured where there was dispute.
a. For the M&E design it was stage 3, for the rest it was stage 4.
a. The MEP works constituted most of this, as additional AHU’s were added into the scheme, this further led to the addition of the plant deck (originally priced as an upper floor by the contractor), which added further price.
a. It is a timber structure built and resting on timber stilts which sits and spans across multiple or a single room, above the ceiling. It is used to bear the weight of mechanical and electrical plant when it is unable to be hung from the higher roof structure due to it not being structurally sound enough.
a. I requested the contractor provide 3 quotations for the main works packages, such as MEP, joinery/carpentry, finishes, and FF&E
a. Can mean multiple things, best out of budget, best value per pound for the client
a. There was a 2 month allowance in the original cost plan for inflation, based on an assumed tender and construction period.
a. I utilized the BCIS building cost indices, using the present day and future date as two points in time, dividing the future by the present minus the future, to give me a percentage to apply to the bottom line.
a. I made some minor proposals to the design team for consideration so they could then put forward and advise on. For example from experience on other schemes similar in nature with this client, I was aware that the data cabling could perhaps be substituted from CAT6A to CAT6. I noted that the contractor had proposed £13k for a banksman to be on site during construction, and proposed the question to the client and design team if there was ana alternative, to make use of the new recently erected fencing.
b. Large VE items included the change from an upper floor solution, to a simple plant deck solution to carry the weight of the mechanical plant.
a. Lose sight of purpose, and start omitting important design aspects
b. Could have an impact on whole life cycle costs
a. At the time it was unknown when the project would be tendered, therefore 2 months of inflationary uplift was included and any addition was noted as excluded.
b. I included total contingency in the form of NRM risk allowanced at a total of 10%, as even at that time the design was at stage 3 with no more foreseeable changes.
a. I advised the client I should create a pre-tender estimate based on the updated design, prior to getting tender returns back.
a. These are omitting the works altogether from the project, for example omitting cork wall boarding which was purely aesthetical, which could then be added back in future months as a client direct expense, not falling under the main project budget
a. I didn’t advise on the design of the project, and I know to not do this as this doesn’t fall under my scope of services, and my companies PI cover does not cover liability for construction design.
a. The difference is the data speed that the cable can carry, this produced a saving but both cables still serve the same purpose of data transmission. it is cheaper material.
a. Total saving made was £153k inc scope reduction and negotiated items. (all part of same register)
a. I didn’t advise on the design changes, however I made proposals, and areas of focus as I knew where the main costs were in the design and tender return. I then negotiated costs of these changes with the contractor, and advised on suitable allowances for any provisional sums.
a. I requested 3 quotations from the contractor on the packages of works to ensure commercial value. I also used rates from other recently tendered similar projects, and projects the contractor has worked on.
a. Prepare in advance and highlight areas which perhaps seem erroneous or unreasonable, then hold a meeting where items are ran through, and substantiation is either requested or costs are asked to be lowered or altered, where I would back these up with my own data collection.
a. Clients internal sign off procedures were monthly, so if I produced a cost plan, it would not have resulted in a change due to the timing of reporting.
b. The cost plan was based on the assumption of a competitive tender, but it was eventually negotiated due to timescales, it was widely accepted by the business this would incur increased costs.