CHS Flashcards

(15 cards)

1
Q

Which of the following describes the normal lineup of the charging and letdown portions of the CVCS system?

A

L/D: RCS loop 3 Tc, LCV549 and 460, L/D orifice, demin, VCT
Charging: VCT, charging pump, RCS loop 1 or 4 Tc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following are purposes of the charging and letdown system?

A

provide seal injection flow to RCPs
control RCS coolant inventory
control RCS chemistry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the function of the charging pump safety grade minimum flow recirculation line isolation valves?

A

protect charging pumps during SBLOCA by ensuring a minimum flow path to the RWST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

All the following are purposes of the CVCS except:

A

low head safety injection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following describes the function of the RHR system letdown control valve?

A

provides letdown flow when RHR system is in the S/D cooling mode

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When performing a chemical addition to the RCS, why does the procedure caution to monitor for possible reactivity changes?

A

PGS used to flush chemicals from the chemical add tank could cause reactivity changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

During normal operations, the charging pumps are protected from low flow conditions via mini-flow recirculating line isolation valves, 3CHS*MV8111A/B/C and *MV8110.

What provisions are made to protect the charging pumps against low flow conditions in an emergency situation?

A

mini-flow recirc lines isols. *MV8111A/B/C and *MV8110 close and the safety grade mini-flow recirc lines *MV8511A/B open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of the interlock which prevents opening or closing letdown isolation valves, prior to letdown orifice isolation valves being closed?

A

to protect the regen HX from damage due to high temp/low pressure L/D flow from flashing to steam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What emergency signal automatically positions RCP seal return isolations, and letdown line containment isolation valves?

A

CIA signal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following statements describes the relationship between the charging and letdown flow passing through the regen HX during steady state operation?

A

letdown flow higher than charging flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Plant at 100%

SBLOCA occurs
Crew starts second charging pump
Crew actuates SI
RCS pressure decreases/stabilizes

What is the expected position of the VCT outlet valves (CHSLCV112B/C) and the charging cold leg injection valves (SIHMV8801A/B)?

A

CHSLCV112B/C: closed
SIH
MV8801A/B: closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where in the AB is 3CHS*V14 the bypass valve for letdown pressure control valve located?

A

AB 4’ general area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of placing *DEMN2 in service in the RCS letdown line when it is full of anion resin?

A

be an alternate method for deborating the RCS at end of core life

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the purpose of placing *DEMN2 in service in the RCS letdown line when it is full of cation resin?

A

remove lithium from RCS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SI was manually actuated and all ECCS equipment operated.

What describes the response of the following CVCS components:

RCP seal return isolation valves
charging flow control isolation valves

A

RCP seal return isolation valves *MV8100 and 8112 CLOSED on CIA
Charging flow control isolation valves *MV8105 and 8106 CLOSED on SI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly