What does ‘time’ in a contract refer to?
The time by which a party’s obligations under the contract must be performed and the consequences if they fail.
What is the general consequence of failing to perform obligations on time?
Breach of contract, which may give the other party the right to terminate and/or sue for damages, subject to contractual mechanisms.
Why is ‘contract is king’ important in time management?
Because all rights, obligations, and remedies (including delays and termination) are governed by the contract’s terms.
Define practical completion.
The point at which a building is fit for its intended use.
What are the usual requirements for practical completion?
What happens once practical completion is reached?
Start of defects liability, final account reconciliation, release of security, end of contractor’s possession and risk.
Who initiates the practical completion process?
The contractor, by giving written notice with a schedule of defects/incomplete works.
What is the architect’s role in practical completion?
Inspect works, issue notice of practical completion or defects, act independently and impartially, meet deadlines.
How long does the architect have to inspect after the contractor’s practical completion notice?
Within 10 days or an agreed period.
What happens if practical completion is not reached by the required date?
Architect must notify contractor and owner in writing of owner’s entitlement to liquidated damages.
When does the owner release security after practical completion?
Typically 50% at practical completion, remainder after defects liability period and final certificate.
What is the defects liability period?
The period during which the contractor must correct defects and incomplete works, usually 12 months, sometimes 24 months if specified.
What if the contractor fails to fix defects in time?
Owner can have a third party complete the works at contractor’s expense.
How long are statutory warranties for residential buildings?
2 years for minor defects, 6 years for major defects.
When is the final certificate issued?
After defects liability obligations are complete and remaining security is released.
What are liquidated damages?
Pre-agreed damages payable for delay or breach of contract.
Why are liquidated damages used?
Provides certainty of losses, avoids proving actual loss, allows contractor to calculate cost of acceleration.
Can liquidated damages be enforced if the principal contributes to delay?
No; principal-caused delays may invalidate enforcement, mitigated by Extension of Time clauses.
When must the architect notify of owner’s entitlement to liquidated damages?
Promptly, once the date for practical completion is reached but works are incomplete.
What is required for liquidated damages to be valid?
Must be a genuine pre-estimate, not a penalty or extravagant.
What is an Extension of Time (EOT)?
A contractual mechanism to adjust the practical completion date due to qualifying delays.
What are the main elements of an EOT claim?
What are the notice requirements in ABIC for delay events?
Contractor must notify the principal within 2 working days of awareness of start and end of delay event, in writing, including cause, start date, and estimated impact.
How long does the contractor have to submit a claim for adjustment?
Within 20 days of the delay event.