System Design and Development Flashcards

(52 cards)

1
Q

Five (5) key agencies in systems design:

A
  • Society of Automobile Engineers (SAE):
    ARP 4754 [1]
    ARP 4761 [2]
  • Federal Aviation Authority (FAA):
    AC 25.1309-1A [3]
  • Joint Airworthiness Authority (JAA):
    AMJ 25.1309 [4]
  • Air Transport Association (ATA):
    ATA-100 [5]
  • Radio Technical Committee Association (RTCA):
    DO-178b [6]
    DO-254 [7]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

It is a set of design processes.

A

ARP 4754

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It represents a set of tools and techniques.

A

ARP 4761

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

It offers advice for the design and certification of software.

A

DO-178B Overview - Design Assurance for Airborne Software

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

It offers guidance for hardware design and development.

A

DO-254 Overview – Design Assurance Guidance for Airborne Electronic Hardware

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

It is carried out at both aircraft and system levels; one flows down from the other.

A

Functional Hazard Analysis (FHA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It identifies system failures and identifies the effects of these failures.

A

Functional Hazard Analysis (FHA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The FHA identifies the data in first two columns of the table: the _ and the _.

A

failure condition classification; development assurance level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

It examines the failure conditions established by the FHA(s) and demonstrates how the system design will meet the specified requirements.

A

Preliminary System Safety Analysis (PSSA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

It is part of an iterative process which scrutinizes the system design and assists the system designers in ascribing and meeting risk budgets across one or a number of systems.

A

Preliminary System Safety Analysis (PSSA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Increasingly, given the high degree of integration and interrelationship between major aircraft systems, this is likely to be a multi-system, multi-disciplinary exercise coordinating the input of many systems specialists.

A

Preliminary System Safety Analysis (PSSA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

It is a systematic and comprehensive evaluation of the system design using similar techniques to those employed during the PSSA activities.

A

System Safety Analysis (SSA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

It is intended to verify that the proposed design does in fact meet the specified requirements as identified during the FHA and PSSA analyses conducted previously.

A

System Safety Analysis (SSA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

It occurs at the point in the design cycle where the system implementation is concluded or finalized and prior to system certification.

A

System Safety Analysis (SSA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It begins concurrently with the system FHA and is interactive with this activity and subsequent PSSA and SSA analyses.

A

Common Cause Analysis (CCA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Its purpose is to identify common cause or common mode failures in the proposed design and assist in directing the designers towards strategies which will obviate the possibility of such failures.

A

Common Cause Analysis (CCA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

It is one of the tools described in SAE document ARP 4761.

A

Fault Tree Analysis (FTA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

This analysis technique uses probability to assess whether a particular system configuration or architecture will meet the mandated requirements.

A

Fault Tree Analysis (FTA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Component of electrical power generation systems that governs voltage regulation and system protection.

A

Generator Control Unit (GCU)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The seven (7) major phases of the product life cycle:

A
  • Concept Phase
  • Definition Phase
  • Design Phase
  • Build Phase
  • Test Phase
  • Operate Phase
  • Refurbish or Retire
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

It is the set of actions associated with the upkeep of a type design and the associated approved data through life.

A

continued airworthiness

22
Q

Two (2) other terms for continued airworthiness.

A
  • type airworthiness
  • initial airworthiness
23
Q

This phase is about understanding the customer’s emerging needs and arriving at a conceptual model of a solution to address those needs.

A

Concept Phase

24
Q

This phase is focused on establishing confidence that the requirement can be met within acceptable commercial or technological risk.

A

Concept Phase

25
The establishment of a baseline of mature technologies may be first solicited by means of a _.
Request for Information (RFI)
26
A common feature used more frequently by platform integrators is to establish engineering joint concept teams to establish the major system requirements. These teams are sometimes called _.
Integrated Product Teams (IPTs)
27
The IPTs may develop a cardinal points specification; perhaps even undertake a preliminary system or baseline design against which all vendors might bid. This results in the issue of a specification or a _.
Request for Proposal (RFP)
28
equipment electrically equivalent to the final product but not physically representative
electrical models
29
equipment which is physically representative but not cleared for flight
red label hardware
30
equipment which is physically representative and is cleared for flight either by virtue of the flight-worthy testing carried out and/or the software load incorporated
black label hardware
31
The aircraft and its components are subject to a rigorous test programme to verify its fitness for purpose. This phase – usually referred to as _, includes testing and integration of equipment, components, sub-assemblies, and eventually; the complete aircraft.
qualification
32
_ of equipment and systems on the ground and flight trials verifies that the performance and the operation of the equipment is as specified.
Functional testing
33
Conclusion of the test programme and the associated design, analysis and documentation process leads to _ of the aircraft or equipment.
certification
34
During this phase, the customer is operating the aircraft on a routine basis.
Operate Phase
35
In the operate phase, aircraft performance will be monitored by means of a _, so that any defects or faults that arise are analyzed by the manufacturer.
formal defect reporting process
36
It may be determined by unacceptably high operating costs, unacceptable environmental considerations – noise, pollution etc. – or by predicted failure of mechanical or structural components determined by the supplier’s test rigs.
end of life
37
It is the first top-level, multi disciplinary review of the perceived system requirements.
System Requirements Review (SRR)
38
It is effectively a sanity check upon what the system is required to achieve; a top level overview of requirements and review against the original objectives.
System Requirements Review (SRR)
39
Successful attainment of this milestone leads to a preliminary system design leading in turn to the parallel development of the hardware and software requirements analysis, albeit with significant coordination between the two.
System Requirements Review (SRR)
40
The hardware _ immediately follows the preliminary design phase and will encompass a top-level review of the system hardware characteristics such that preliminary design may proceed with confidence.
System Design Review (SDR)
41
Key hardware characteristics will be reviewed at this stage to ensure that there are no major mismatches between the system requirements and what the hardware is capable of supporting.
System Design Review (SDR)
42
It is essentially a similar process to the hardware SDR but applying to the software when a better appreciation of the software requirements has become apparent and possibly embracing any limitations such as throughput, timing or memory which the adopted hardware solution may impose.
Software Specification Review (SSR)
43
This process is the first detailed review of the initial design (both hardware and software) versus the derived requirements.
Preliminary Design Review (PDR)
44
This is usually the last review before committing major design resource to the detailed design process.
Preliminary Design Review (PDR)
45
This stage in the design process is the last before major commitment to providing the necessary programme resources and investment.
Preliminary Design Review (PDR)
46
By the time of the _, major effort will have been committed to the programme design effort.
Critical Design Review (CDR)
47
It offers the possibility of identifying final design flaws, or more likely, trading the risks of one implementation path versus another.
Critical Design Review (CDR)
48
It represents the last opportunity to review and alter the direction of the design before very large commitments and final design decisions are taken.
Critical Design Review (CDR)
49
Major changes in system design – both hardware and software – after the _ will be very costly in terms of cost and schedule loss, to the total detriment of the programme.
Critical Design Review (CDR)
50
It determines how far a twin-engine plane can safely and legally fly from the nearest suitable airport for an emergency landing.
Extended-range Twin-engine Operational Performance Standards (ETOPS)
51
Twin-engine planes were originally restricted by the "_," meaning they had to fly within 60 minutes of an airport in case of an engine failure.
60 Minute Rule
52
ETOPS certification is granted in increments (e.g., ETOPS 120, ETOPS 180, ETOPS 330), where the number represents the maximum number of _ a plane can be from a suitable airport while flying on a single engine.
minutes