You mention that your company were appointed on the project since 2020. Was this highlighted as a risk?
How did you quantify the risk of the drains, prior to undertaking the CCTV survey?
Why did you undertake CCTV surveys before December 2023, if you knew it was such a risk?
There were two main reasons:
(1) Vacant Possession of the building was acheived in late December 2022, which meant that it was not possible to undertake any surveys as we did not have possession of site.
(2) NWR confirmed that any works within 3m of the OLE required full isolations and possessions. There were no such isolations available prior to December 2023, when a one day blockade was in place over Christmas.
Given the works were non-intrusive, did you ever think to do the initial surveys without NWR approval?
No, this was never a consideration, as I felt it would contradict with the RICS Rules of Conduct. Namely, it would not be acting with (1) Integrity, and (2) would not promote trust in the profession.
It would also put my Client at risk if anything went wrong, which contradicts rule 3, which is ensuring good quality output.
It also would not comply with the RICS ethical decision making tree, as I would not be able to justify this externally, could be deemed illegal (as it contravened the Basic Asset Protection Agreement) with NWR, and I would not be happy if it was made public (even if the works were undertaken succesfully).
Why did you not seek to get the Main Contractor to take on the risk as part of their scope of works?
This was discussed during the PCSA, however the Main Contractor was not willing to take on the risk. This was because they did not feel they had adequate information to effectively price the risk, and therefore would not take the risk for this scope of works.
How did you tender for the drainage contractor?
(1) Contractor had to be NWR approved, in order to undertake works on or near the OLE.
(2) Contractor had to have adequate PLI at £50m, which was a NWR requirement under the Clients Basic Asset Protection Agreement
What contract did you use to undertake the works? Why was this Contract used?
This was chosen because:
1) Contract value was less than £500k
2) Works would be undertaken in 4 days
3) Did not require any contractor design (save for the use of a podium scaffold tower)
4) Contained provision for insurance requirements, and established the risks between both parties.
How did you establish what options were going to be assessed?
Following the receipt of the survey, I instructed the design team and the CCTV contractor to provide a list of alternative options.
I ensured each consultant / contractor were effectively briefed on the requirements, and what the client was seeking to acheive (i.e. ensuring that waste and water could be removed from the south core to the shared sewer on Bishopsgate)
Were any other options presented?
No, there were variations of each of the options, however themeatically, these were the only three available alternatives.
There were suggestions that different pipework routing for option 3 could be proposed (i.e. the diverted pipework would exit the buildings facade and enter the basement and sewage externally) however this was discounted as it would have had a planning implication.
How did you establish the assessment criteria?
Were any other criteria discussed?
Other criteria were discussed, namely the service life that each option would result in.
However, following discussion with my client, any option that did not come with a 20-year service life, or 12-year warranty was immediately discounted.
How did you determine the weighting of each option?
How did you establish what scored a 1 and what scored a 3 in the performance?
You mention that the cost for the adopted solution exceed the commercial value in the risk register – how did the Client react?
What was the value implication of Option 3 if it were pursued?
If option 3 were pursued, would any other works be required?
Yes, it would have required new capping on the previous gulleys, and screeding over the GF slab.
NWR did not require the existing pipework to be removed.
What was the remaining service life of the other drains that were assessed?
As part of the initial CCTV surveys, the drainage contractor confirmed that they had a remaining servicable life of 20 years.
Were there any amendments to the contract that you used?
There were two main amendments made to the contract:
(1) Limit of Contractors Liability - Under the amended JCT Minor Works there was no limit of liability. This was limited to 150% of the Contract Sum, noting the potential risks to the railway.
(2) Rectification Period - Amended to 12-months from 6 months, to reflect the fact that the blockades happen every Christmas, so facilitated a mechanism by which the Contractor could feasibly come back and undertake rectification works.
You mention that failure to complete the scope would impact the Main Contractors programme, and cause a risk to the Client, how was this captured under the Building Contract you used?
Clause 2.27 of the JCT D&B Contract dealt with Relevant Events.
Under this, a named relevant event was delays caused by the Employer. If the drains were not in working order, this would constitute a Relevant Event, and would mean that the Contractor was eligible for an Extension of Time.
What is a sump pump? How would this solution work?
A mechanical system used to remove water or waste from a low-lying area.
The system would collect waste and water, once it had reached a certain point, the pump would activate and divert it away from the building at high level.
Talk to me about the issues with the specialist drainage contractor confirming their prices?
The drainage contractor were not able to confirm the costs for the water tankers in line with the programme (which assumed that a fixed price was confirmed 2 months prior to the works).
This meant that the cost consultant only had a week to review the costs of the works, as opposed to the two that I had accounted for in my programme.
What is the breakdown of the JCT Minor Works Contract?
Section 1: Articles of Agreement - The identities of both parties, construction sum etc.
Section 2: Contract Particulars - Dates, damages, insurance etc.
Section 3: Conditions - The terms of the contract
Section 4: Execution of the contract