Contract Practice (L3) Flashcards

(88 cards)

1
Q

What is a contract?

A

A contract is an agreement enforceable by law, which establishes the rights and obligations of two parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the requirements of a valid contract?

A

For a contract to be valid, there must be:

1) An offer - a clear proposal by one party to enter into an agreement.
2) Acceptance of the offer - agreement to the terms of the offer.
3) Consideration of the offer - something of value must be exchanged (usually money)
4) Intention to create legally binding relations
5) Capacity to form a legal agreement - i.e. over 18, sound of mind
6) Authority to form a legal agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key differences between NEC & JCT

A

There are a variety of differences between the JCT and the NEC, including:

1) Approach / Risk: JCT assigns risk more clearly, whereas the NEC encourages a more collaborative approach.

2) Programme: The programme is not a contractual document under the JCT, whereas it is under the NEC. Under an NEC, the Contractor must keep the programme current, outline early warnings and update on progress. The programme must also be issued on a monthly basis for approval.

3) Administration: The contract is administered by a Contract Administrator or Employers Agent, whereas it is administed by a Project Manager in an NEC/

4) Cost: JCT is typically a lump sum contract, whereas an NEC offers a more flexible cost mechanism with six different pricing options.

5) Time / Delay: Under a JCT there are relevant events which can entitle the contractor to more time, whereas in an NEC there are 20 compensation events. JCT also deals with time and money separately (under relevant events and relevant matters). NEC treats them together as compensation events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What factors influence the selection of the most appropriate form?

A

1) Size and nature of works (complexity, value, type) e.g. NEC more appropriate for infrastructure.

2) Experience of the client e.g. JCT minor works appropriate for inexperienced client

3) Familiarity / market being worked in – in UK, JCT very popular and well known

4) Risk allocation and design responsibility

5) Procurement Route

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a loss and expense claim?

A
  • A claim by the contractor for costs incurred due to a Relevant Matter under the contract e.g. Failure to give possession
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are LADs?

A
  • Liquid and Ascertained Damages – costs payable by the contractor if the project runs past the agreed completion date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the benefit of using standard forms of contract?

A

There are a variety of benefits of using a standard form of contract, including:

1) Time Saving - These contracts are ready made, reducing requirement to draft from scratch.

2) Proven and Tested - They are widely used in the industry, reducing uncertainty and errors.

3) Cost Savings - Due to not having to draft from scratch.

4) Familiarity - Administration is smoother.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What would you consider when selecting a contract?

A
  1. Type and Nature of the works
  2. The specific procurement route undertaken
  3. Value of the works
  4. Experience of the client
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What insurances are you aware of that can relate to contracts?

A

1) Professional Indemnity Insurance (PI)
2) Public Liability Insurance (PLI)
3) Construction All Risk Insurance (CAR)
4) Latent Defects Insurance (LDI)
5) Employers Liability Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a bond?

A
  • A bond is a form of financial guarantee provided by a third-party surety (such as an insurance company or a bank) to protect the project owner (also known as the obligee) from financial loss in case the contractor (also known as the principal) fails to meet the obligations outlined in the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Parent Company Guarantee?

A
  • A contractual agreement in which a parent company agrees to take responsibility for the performance of a subsidiary company’s obligations under a specific contract.
  • If the subsidiary (the principal) fails to meet its contractual duties, the parent company (the guarantor) steps in to fulfill those obligations or compensate the other party (the beneficiary or obligee) for any losses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an Employers Agent?

A
  • A professional or organization appointed by the employer (the client or project owner) to act on their behalf and manage the contract, particularly under Design and Build (D&B) contracts.
  • Manages the day to day administration of the contract and ensures that each party is fulfilling their contractual obligations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are Third Party Rights?

A

Legal entitlements that individuals or entities who are not directly involved in the contract (third parties) may have to enforce certain rights or benefits under that contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the differences between collateral warranties and TPRs

A

A collateral warranty is a seperate contract that gives a third party direct rights against a contractor or consultant, which provides direct enforceable obligations.

A third party warranty is a statutory or contractual mechanism that allows a third party to enforce specific rights under the main contract without being a signatory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Give me an example of a collateral warranty?

A

For example, under a JCT D&B contract, a collateral warranty is often agreed between the Client and Subcontractors which means that the Client can directly enforce contractual terms with the subcontractor.

These can be different to the terms established under the main contract, for example a third party can have a collateral warranty with a subcontractor with an extended liability period than the main contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give me an example of a third party right?

A

For example, affording a tenant for a future building to enforce the standards under the existing contract. For example, directly calling for defects to be rectified.

However, they are limited to what the contract or statute allows. E.g. they can not call for a contractor to resolve defects over and above the defects liability period under the main contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What examples of contract are you aware of?

A

1) Construction Contracts
2) Consultant Appointmnets
3) Lease Agreements
4) Third Party Agreements (Party Wall Agreements)
5) Planning Obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the standard forms of construction contract in the UK?

A

1) Joint Contracts Tribunal (JCT)
2) New Engineering Contract (NEC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the JCT?

A

The Joints Contract Tribunal are a company who produce standard forms of construction contracts and guidance notes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the key features of JCT Contracts?

A

1) Clarity and Consistency: Includes standardised clauses to avoid reinventing contracts for each project.

2) Risk Allocation: Clearly sets out responsibilities for time, cost, quality, risk etc.

3) Dispute Resolution: Provides mechanisms for dispute resolution (such as adjudication, arbitration, mediation etc.)

4) Different forms of JCT available to suit different procurement routes adopted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What types of JCT contract are there?

A

There are a variety, however the main forms are:

1) JCT Standard Building Contract

2) JCT Design & Build Contract

3) JCT Intermediate Build Contract

4) JCT Minor Works Contract

5) JCT Major Project Construction Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is a JCT Standard Building Contract?

A

A JCT Standard Building Contract is used for large, complex project where the employer provides the full design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is a JCT Design and Build Contract?

A

Used for medium to large projects. The client sets out the Employers Requirements, and the contractor responds with their Contractor Proposals on how they will design and deliver the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a JCT Intermediate Build Contract?

A

Suitable for medium sized projects with straightforward construction, however the project would require more administration than Minor Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is a JCT Minor Works Contract?
Suitable for small or straightfoward construction projects (such as repair works). Projects with a short duration, simple scope and limited risk.
26
What is a JCT Major Project Construction Contract?
The largest and most sophisticiated form of JCT, for very large, complex construction projects. Offers flexibility to amend risk allocation and administrative procedures.
27
What is the NEC?
The New Engineering Contract are a suite of contracts published by the Institution of Civil Engineers. For example, the NEC Engineering and Construction Contract, or the NEC Professional Services Contract.
28
What are the key features of the New Engineering Contracts?
1) Flexibility - Can be used for different procurement methods 2) Collaboration - Designed to encourage good project management and collaboration 3) Purpose - Commonly used in infrastructure, civil engineering and large commercial projects
29
What types of NEC Contract are there?
There are six main variants to the NEC Contract: Option A - Lump Sum (Fixed Price) Option B - Priced Contract with Bills of Quantities Option C - Target Contract with Activity Schedule Option D - Target Contract with BOQ Option E - Cost Reimbursable Contract Option F - Management Contract
30
What is the NEC Contract Option A?
Option A - Lump Sum (Fixed Price) The Contractor is paid a fixed price for defined activities in a lump sum. The contractor bears the cost risk.
31
What is the NEC Contract Option B?
Option B - Priced Contractor with BOQ The Contractor is paid for actual quantities exectued at agreed rates. The risk is shared.
32
What is the NEC Contract Option C?
Option C - Target Contract with Activity Schedule Both parties agree a target cost; the actual costs are measured; the contractor is compensated for over/under target as per the agreed form. Ie. if the final cost is below the target, savings are shared between the employer and the contractor. Equally, if the final cost is above the target, the overrun is shared.
33
What is NEC Contract Option D?
Option D - Target Contract with BOQ Same as option C, but using a bill of quantities for measuring work
34
What is NEC Contract Option E?
Option E - Cost Reimbursable Contract Contractor is reminbursed for actual costs + a fee
35
What is NEC Contract Option F?
Option F - Management Contract Contractor manages subcontracts for works packages, like in a construction management procurement route.
36
What is PI?
Professional Indemnity Insurance protects professionals against claims arising from negiligence, errors or omissions in their professional services.
37
What is CAR?
Construction All Risk is a comprehensive insurance policy covering physical loss or damage to a construction project during the construction period.
38
What is Employers Liability Insurance?
Insurance that protects an employer against claims made by employees who suffer injury, illness or death as a result of their work. It is legally required for most employers in the UK.
39
What is public liability insurance?
Public Liability Insurance – Insurance against claims made by third parties for injuries or property damage that occur as a result of the business's activities or operations
40
What is Latent Defects Insurance?
Latent Defects Insurance - provides protection for property owners and developers against defects in the design, workmanship, or materials that may not be immediately visible after the completion of a construction project but become apparent over tim
41
What is a warranty?
A warranty is a formal guarentee given by a contractor, supplier or manufacturer that a product will meet specified standards, quality and performance for a defined period.
42
What forms of warranties are you aware of?
1) Contractor Warranty 2) Manufacturer Warranty 3) Latent Defects Warranty 4) Collateral Warranty
43
What is a Contractor Warranty?
A contractual guarentee given by the contractor that the works will be carried out in accordance with the contract documents. A contractor warranty provides the client with legal recourse if the contractor fails to deliver the works to an agreed standard.
44
What is a Manufacturer Warranty?
A guarentee that the materials, equipment or product will meet specified performance and quality standards
45
What is a Latent Defects Warranty?
A warranty provided by the contractor covering hidden or structural defects in the completed works that become apparent after practical completion and were not detectable at handover.
46
What is a collateral warranty?
A separate legal agreement that extends the rights and obligations of a contractor, consultant or subcontractor to a third party. In essence, it provides direct contractual rights to a third party who is not the original employer. I.e. Between a client and a subcontractor.
47
What is a Third Party right?
A legal mechanism established under the Contracts Act 1999 that allows a person or entity (i.e. lenders, tenants, funders) who is not a party to a contract to enforce specific terms of that contract.
48
What is the difference between a collateral warranty and a third party right?
A collateral warranty is a separate, new agreement with a third party. A third party right arises from the main contract, with no new agreement needed.
49
What documents are usually included in a JCT D&B Contract?
Volume 1: Contract Agreement and Conditions of the Contract (e.g. design responsibilities, variations, completion, payment etc.) Volume 2: Employers Requirements (e.g. ETRs, Planning Obligations, PC Checklist, Employer Policies) Volume 3: Contractors Proposals (Design Submissions, Technical Proposals, CSA, Programme)
50
What are Employer's Technical Requirements?
The detailed technical and functional requirements that the employer expects the contractor to meet under a design and build contract.
51
What would usually be included in ETRs?
1) Performance requirements - e.g. acoustic performance, fire resistance, structural capacity 2) Materials standards 3) Sustainability / Environmental requirements 4) Testing / commissioning and handover requirements.
52
Why did you recommend a JCT Minor Works Contract for the drainage repair works?
1) The works were an emergency with leaks impacting a third party. Therefore a standard form of contract needed to be chosen. 2) The works were simple, and required replacing a section of pipework. There was no design required. 3) It was a short programme with all works to be completed in one go.
53
Why did you recommend a JCT D&B contract on the 1 Finsbury Avenue project?
I recommended a JCT D&B contract due to the clients requirements on cost, programme and risk. 1) The project was to deliver a floor of CAT A onto a now vacant floorplate. The clients key drivers was to reduce the void and return to market asap, whilst also reducing risk and establishing cost certainty. 2) JCT D&B allowed a: 1) reduced procurement timescales for a design team and a contractor - contractor does both 2) programme efficiency - allowed the contractor to commence strip-out works whilst also commencing design 3)
54
What is sectional completion?
When a contractor completes different parts or sections of a project at different times, rather than waiting for the entire project to be finished.
55
What were the contractual obligations undertaken during the sectional completion process?
1) Contractor notification of sectional completion 2) Site visits with professional team to establish whether works have been completed 3) Establishment of any outstanding works / snags, and rectification time scale 4) Compliance statements by the design team 5) Handover of key information (inc. O&Ms and HSF)
56
What is defects rectification?
Defects rectification is the process by which a contractor remedies faults, deficiencies, or non compliance issues during the defects liability period.
57
What is the purpose of a contract?
- Set out the rights and obligations of parties - Set out rules and procedures - Transfer risk
58
What is a standard form of contract with variations?
When a standard form of contract is taken but some key provisions are amended and documented under the schedule of amendments (e.g. LADs, retention, payment periods)
59
What is an extension of time?
A formal adjustment to a contractual completion date granted to the contractor when delays occur outside of their control (Relevant Event)
60
What are the benefits of granting an extension of time?
1) Relieves the contractor's liability for LDs 2) Enables another completion date to be set, which maintains the employer's ability to deduct LDs if another delay occurs.
61
What needs to be in place before LD's can be deducted?
A non-completion ceritificate ; a witholding notice
62
What is retention?
A portion of the contract payment witheld by the employer to ensure that the contractor properly completes the works and rectifies defects. Usually 5 - 10%.
63
When is retention released to a contractor?
Half is issued at practical completion, the other half is isssued at the completion of the defects liability period.
64
What is Practical Completion?
The stage in the construction project where the works are substantially complete, allowing the employer to take possession and use the building for its intended purpose. Administered by the Contractor Administrator. Minor defects or omissions can persist.
65
What is a Non Completion Certificate
A certificate issued by the contract administrator when the works have not reached practical completion by the agreed completion date. May trigger contractual remedies such as liquidated damages.
66
What are the time periods for dealing with EOT claims under construction contracts?
JCT - The Contractor should inform of a Relevant Event when a delay becomes reasonably apparent. The administrator must provide notice of a decision within 12 weeks of evidence receipt. NEC - The Contractor must give notice within 8 weeks of the event that a delay has been caused. The PM has 1 week to make a decision.
67
When can a contract be terminated?
1) Contractor fails to comply with obligations and has not corrected them within 4 weeks. 2) The Contractor has assigned or changed any rights and benefits of the contract. 3) Legal ownership of the Contractor has changed.
68
What different types of bond are you aware of?
1) Performance Bond 2) Advanced Payment Bond 3) Retention Bond
69
What is a performance bond?
A third party (typically a bank or insurer) takes responsibility for the performance of a contractor. If the contractor does not meet their contractual obligations, the surety pays the client compensation (typically 10% of the contract value)
70
What is an advanced payment bond?
If the client agrees to pay the contractor in advance (e.g. for site set up costs incurred befored the contact begins), an advanced payment bond is held by the surety in case the contractor fails to meet their contractual obligations, and the client needs to be reimbursed.
71
What is a retention bond?
Instead of agreeing to retention, the client pays the retention upfront. If the contractor does not fulfil their contractual obligations, the surety pays the retention value to the client.
72
What is a Net Contribution Clause?
A contractual clause which limits the liability apportioned to each contracting party. The apportionment is limited to the fair and reasonable amount that a court would apportion against it. For example: A significant defect occurs on site. The total loss to the developer is £100k. Without a net contribution clause, the Client would only be able to recover the costs from the main contracting party. With a net contribution clause, each party is only liable for the loss they have caused (i.e. 70% structural engineer, 20% architect, 10% contractor).
73
What is assignment?
The transfer of interest or benefit from one person to another. Note: the burden or obligations, cannot be transferred. I.e. a Developer sells a building following completion, but wants to assign its rights under the contract to the new owner.
74
What is novation?
A contractual mechanism by which a new contract is entered into which transfers both the rights and obligations of one contractual party to a new third party. E.g. in a design and build contract, where the contractor takes on the design responsibility, the existing appointments (including rights and obligations) are transferred over to the contractor.
75
What legislation is relevant to contracts?
The Local Democracy, Economic Development and Construction Act 2009.
76
What is the Construction Act 2009?
A piece of UK legislation that brought in important changes to the payment and adjudication process in construction contracts. The aim of the act is to improve the cashflow process in construction contracts and ensuring a swift resolution for resolving disputes. Key principles include: 1) Prompt Payment - Requires that construction contracts include provisions for regular and timely payments. 2) Adjudication - Establishment of a statutory right to adjudication in construction contracts. 3) Payment Notices - Act introduces the concept of payment notices - this requires the payer to issue payment notices indicating the sum due. If there is a dispute, the payee can issue a notice of intention to refer the dispute to adjudication. 4) Prohibition of "Pay when Certified" Clauses - act prohibits contractual clauses that make payment dependent on the issurnace of a certificate.
77
What is the relationship between the HGCRA 1996 Act and the Construction Act 2009.
The Housing Grants, Construction and Regeneration Act 1996 introduced the: 1) Statutory Right to adjudication 2) Statutory Payment Regime 3) Right to Suspend Works for non-payment The Construction Act 2009, was the amending act which updated some of the key provisions, including: 1) Contracts no longer have to be in writing. 2) Tighter payment provisions - introduced the default payment notice (if the payer fails to serve a payment notice, the payee's application stands) 3) Improved right to suspend for non-payment - contractors can suspend part, but not all, of the works, and now have the right to recover reasonable costs and expenses of suspension.
78
What are the key changes between JCT 2016 and 2024
(1) Use of gender neutral language throughout (replacement of pronoun "him" when referring to a Contractor. (2) Inclusion of Epidemics as a standard Relevant Event. (3) Reduction in the amount of time a Client has to review an respond to a Notice of Delay, from 12 weeks to 8 weeks.
79
What are secondary X clauses in the NEC?
* Secondary X clauses are optional provisions that allow parties to tailor the contract to suit the project's commercial, legal or procedural needs. Examples include: X1: Price adjustment for inflation X5: Sectional Completion X16: Retention
80
How does the NEC encourage collaboration.
Core Clause (10.2) is a specific clause which states that the NEC is based on a "spirit of mutual trust and co-operation" Early Warning Mechanisms - both parties must give Early Warning Notices as soon as they become aware of any matter that could increase cost, delay completion or affect performance. Programme Management - Requires the Contractor to maintain and update the programme.
81
What is the Change Control process on One Exchange Square?
82
What is an Easement?
A legal right enjoyed by one piece of land over another piece of land. For example a Right of Way.
83
What is an Options Agreement?
A legal agreement giving one party the right to buy or take a lease of land from the landowner within a specified period, and on pre-agreed terms.
84
How is a Contract executed?
Two main ways: (1) Under Hand - Agreements signed by an authorised individual. No witness required. Limitation period of 6-years. (2) Executed as a Deed - A more formal legal agreement, expressed clearly as a deed, and must be signed by 2 authorised signatories, or by a single director in the presence of a witness. Limitation period of 12-years.
85
What is a Compensation Event under the NEC?
An event that changes the Contractor's cost, time or both and for which the Client accepts contractual responsibility. There are 21 in total, including: (1) Late Possession of Site (2) Unexpected Physical Conditions (3) Additional Scope.
86
What is an amendment to a JCT?
A change or modification to the standard form of drafting under the JCT. These can be undertaken via a bespoke Schedule of Amendments document, or by embedding amendments into the JCT Drafting.
87
What amendments were undertaken to the JCT on a project you have worked on?
(1) Inclusion of proscriptive LAD's in the Contract. (2) Clarification of existing structure risk - provision that the Contractor takes responsibility for all above ground risk, below ground stays with the Client. (3) Payment Durations - from 14 to 28 days from the due date.
88
What are the different insurance options under a JCT?
Insurance Option A - Contractor Arranged Insurance - Contractor is responsible for taking out and maintaining insurance on the works during construction Insurance Option B - Employer - Arranged Insurance - Employer arranges and maintains insurance Insurance Option C - Joint Insurance