What is a programme?
A tool used to manage and track a project
What are the key components of a programme?
Activities
Durations
Dependencies
What different techniques could you use to produce a programme?
GANTT Charts - A visual project management tool that displays the total timeline of a project
PERT - Programme Evaluation and Review Technique
What is the difference between PERT and GANTT charts?
Representation – A GANTT chart represents tasks on a timeline, while a PERT chart focuses on task sequences and dependencies
Focus – PERT charts are more focused on the relationships between tasks and the project’s critical path, while GANTT charters are more focused on the schedule and timing of tasks
Complexity – PERT charts are more complex, especially for large projects with many dependencies.
What is the Critical Path?
What is a Critical Path Analysis
What is the process of a Critical Path Analysis?
What is “Float”?
Who owns the Float in a project?
What is a forward pass?
What is a backward pass?
How do you make a programme?
1) Consult the project brief – what is the end goal, and timeline for achieving it?
2) Identify what the key milestones are – i.e. when is Practical Completion required to be? When is planning permission required?
3) Identify each of the project tasks, duration and sequencing required
4) Get buy in from the rest of the team – i.e. does your planning consultant agree that your proposed duration for planning approval work?
5) Input these into a programme of your choosing – e.g. PERT or GANTT Chart
How do you analyse performance against a programme?
Droplines
* A line draw on the programme with a specific date. Activities behind schedule will cause the line to zag left.
* A simple way to identify what the project status is
* However, it dosen’t identify the cause of the delay
Baselines
* Measures performance vs the planned programme
* For example, the baseline could be at the point at which you are four weeks away from completion – if this isn’t the case then you’re behind programme.
What is earned value analysis?
What is earned value analysis?
What is acceleration?
How do you achieve acceleration?
What are the issues with acceleration?
What are the different contractual positions on programmes?
What are the benefits of a GANTT chart over a PERT?
1) Clarity - GANTT charts are visually simpler
2) Time focus - GANTT charts focus on when activities happen and for how long
3) Overlapping activities - GANTT charts show which activites overlap and run at the same time.
4) Shows the critical path
What is the purpose of a programme?
1) Model the delivery of a project
2) Communicate the plan to the team and client
3) Monitor progress and performance
What are the different types of float?
1) Free Float - The time a task can be delayed before impacting the next dependent activity
2) Total Float - The amount of a time a task can be delayed without affecting the end date of the project
3) Terminal Float - The difference in time between a contractors planned completion date, and the contract end date.
What is a project milestone? Examples?
Project milestones are significant events which impact the delivery of a project.
These are events which may require client sign off, and indicate forward progress.
Examples include: End of stage sign offs, planning submission etc.
What software can be used to create a programme?
1) Asta Powerproject
2) Microsoft Projects
3) Excel
What is concurrent delay?
Concurrent Delay refers to a situation where there are two or more independent delays to the project at the same time.
Both events would have caused a delay to completion independent of the other.
Importantly, the delays are unrelated, and one of which can constitute a relevant event, whereas the other could not.
Typically, in the event there are two causes of delay (and one of which is the employer’s risk), the contractor would get an EOT, but not money.