Is acceleration captured as an instructed change?
Case Study
Do not need a instruction, just formal written communication
Why would a contractor reject a Acceleration?
What was the size of the beam that they believed was on site?
Case Study 2
610×229×101UB
What does this mean in regards to Steel measurement - “610×229×101UB”?
Case study 2
610mm=height
229mm = the Width
101mm = The weight per meter
UB= Universal beam
How do you work out the tonnage of a steel beam?
Case Study 2
Weight per meter x length of beam
What is the rate of a Steel you allow for?
case Study 2
Latest benchmark i have been using is £4500/tn
Excludes for framework, tempoary supports and prelims
What was the originally expected size of the beam?
Case study 2
305x305x95.UB
What were some examples of KPI’s you proposed for Option 2
What is Acceleration?
The process of fast tracking the programme to achieve an earlier completion date
Where are you able to find useful information acceleration?
What are some reasons to accelerate?
Contractor:
1. Free up key staff to work elsewhere
2. Catch up on delayed works
Client:
1.When the knock on affect of not getting site by the orginal day PC date will cost the client more money paying the contractor
Where in the SBC contract do you find information about Acceleration?
Schedule 2 - Variation and Acceleration Quotation Procedures
or Clause 5.3
If the employer wishes to investigate the possibility of of achieving practical completion before the completion date, what needs to happen?
Architect or Contract Administrator shall invite proposals from the contractor
Once the Architects or CA invites the contractor to submit a proposals, what will happen after?
or
What must the acceleration quotation state?
What should the acceleration quotation price for?
How long does a contractor have to provide a quote?
or
Whichever is later
How long doe sthe quaution stay open for?
7 days
What happens if 28 days to prepare and review a accelaration quotation is too long?
Does a Contractor have a duty to accelerate?
Yes - to some extent….
The contractor should take all reasonable steps to mitigate the loss that they would typically allow for.
What wording within the JCT imposes a duty of care to the client?
What did the British westinhouse v Undergorund Electric railways state regarding the duty fo care and a contractors responsibility to accelerate works?
Within the JCT Contract, what does it state that the Contractor’s obligatiuon to delay?
Can a contractor choose to accelerate the works on their own decision?