Case STudy - Beam Size Flashcards

(8 cards)

1
Q

What was Option 1 for Case Study 2

Case Study 2

A

Accellete measures between January and March to maintain existing date of Completion

Included for Backshifts, additional resource, weekend working, costs for additional steel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What did the quotes allow for?

Case Study 2

A

Materials
Additional Prelims (weekend working and Backshifts)
OH&P

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

WHat was the allowance for additional staff for weekend working

Case STudy 2

A

Time and a Half

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was Option 2 for Case Study 2

A
  1. Awarding an EOT specifically for the staircase related works.
  2. Prolongation costs for a five week extension.
  3. Works to be compelted in normal working hours
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risks of Option 2?

Case Study 2

A

Dependant on Goodwin Procters staff opening not hinder the works?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the cost difference between Option 1 & option 2 & Option 3?

Case Study 2

A
  1. Option 1 = £192k
  2. Option 2 = £155k
  3. Option 3 = £216k
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What was Option 3 for Case Study 2

Case Study Nr 2

A
  1. Contractor to complete a 5 week EOT, works in this instance would be completed outside of notmal working hours
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was some of the cost difference between Option 1 & 2 & 3?

Case Study Nr 2

A

Option 2 & 3 included for Hoariding and allowed for prolongation costs and continuation of project insurances.

  1. Hoarding = £5k
  2. Project Insurances = £25k
How well did you know this?
1
Not at all
2
3
4
5
Perfectly