What was Option 1 for Case Study 2
Case Study 2
Accellete measures between January and March to maintain existing date of Completion
Included for Backshifts, additional resource, weekend working, costs for additional steel.
What did the quotes allow for?
Case Study 2
Materials
Additional Prelims (weekend working and Backshifts)
OH&P
WHat was the allowance for additional staff for weekend working
Case STudy 2
Time and a Half
What was Option 2 for Case Study 2
Risks of Option 2?
Case Study 2
Dependant on Goodwin Procters staff opening not hinder the works?
What was the cost difference between Option 1 & option 2 & Option 3?
Case Study 2
What was Option 3 for Case Study 2
Case Study Nr 2
What was some of the cost difference between Option 1 & 2 & 3?
Case Study Nr 2
Option 2 & 3 included for Hoariding and allowed for prolongation costs and continuation of project insurances.