Final Prep Questions Flashcards

(49 cards)

1
Q

```

Name 4 Relevant Events

Contract Practise

A
  1. Variations (SBC) /Changes (D&B)
  2. Suspension due to non-payment
  3. Force Majeure (Relevant Events beyond the Contractor’s control)
  4. Employers Delay - Failure to give access to site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name 4 Relevant Matter

Contract Practise

A
  1. Variations
  2. Failure by the employer to provide access or possession to site
  3. Late issue of information from the client or CA/EA i.e instructions
  4. Delay caused by client direct contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Update from the D&B 2016 to D&B 2024 Contract?

Contract Practise

A
  1. Update terminology and more gender neutral language
  2. Incoporates Building safety Act 2022
  3. EA now has only 8 weeks to review an EOT claim where previously they had 12
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between a minor works contract and a SBC

Contract practise

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between an Advance payment bond an Vestign certificate?

Contract Practise

A

Vesting Certificate: To transfer ownership (title) of off-site goods/materials to the Employer before delivery to site.

Advance Payment Bond: To secure repayment of an advance payment made to the Contractor or supplier before any goods are manufactured or delivered. - Secures payment if goods arent provided

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you use an Advance payment bond an Vestign certificate?

Contract Practise

A

Vesting certificates are a simple legal document, normally signed by the contractor and supplier, confirming the Employer owns the goods.

Advance payment bonds require a bank or surety, with associated fees, security, and legal review, making them more expensive and time-consuming.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are some metrics used for Design economics?

Design Economics

A
  1. £/m2
  2. £/sqft
  3. Cost per unit
  4. Net to gross
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is RevEx?

Business Planning

A

RevEx stands for Revenue Expenditure

RevEx (Revenue Expenditure) is a subset of OPEX that specifically refers to expenses incurred to generate revenue in the current period

Employer Salary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some of the difference between NRM and IPMS when measuring NIA?

Design Economics

A

NRM:
Excludes Columns, stairwells lifts.
Measures to the Internal face of the external walls
**IPMS: **
Excluded; Shared Areas,
Measured to the Internal dominant face of the wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the golden order of pricing for valuating changes?

Design Economics

A
  1. Using Exisitng rates/prices - works of a similar nature
  2. Use Star rates - adjusted rates for different conditions
  3. Make a fair assessment of works (new rates)
  4. Dayworks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When do you meaure Tender inflation from?

Design Economics

A

The period from the estimate base date to the date of tender return.

base date = (when the initial budget is prepared)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When do you meaure Construction inflation from?

Design Economics

A

The period from the date of tender return to the mid-point of the construction period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When giving advice to the client, what was the inflation rate you said was between 2022 and 2023?

Case STudy

A

10% - Based on the Pandemic and Russia and Ukraine war - The market was very volitile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you work out the Inflation?

Case STudy 2

A
  1. Review our companies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the different ways you can deal with Risk?

Risk Management

A
  1. Accept (Accept minor design changes)
  2. Reduce (Complete surveys to reduce risks)
  3. Transfer (Transfer design risk through D&B or insurances)
  4. Avoid/terminate (Change design)
  5. Share (Shared savings clause for VE)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the different WELL Scores?

A

o Bronze = 40-49 points
o Silver = 50-59 points
o Gold = 60-79 points
o Platinum = 80+ points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When is a C.1 replacement schedule used?

Contract Practise

A

Typically in fit-out, refurbishment, or tenant projects where no single party can insure all risks under Options A–C.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a C.1 Replacement Schedule

Contract Practise

A

A bespoke amendment or replacement of the standard JCT Schedule C that’s included when the standard insurance options (A, B, C) don’t fit the project circumstances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is insurance Option C

Contract Practise

A

Existing structures and their contents are insured by the Employer,
while
the Contractor insures the works and site materials.

21
Q

What is Insurance Option B

Contract Pracitse

A

Insurance Option B is used for new-build projects where the Employer is responsible for insuring the works and site materials.

The Employer insures the new works.
There is no existing structure

22
Q

What is Insurance Option A

Contract Practise

A

Insurance Option A is used for new-build projects where the Contractor is responsible for insuring the Works and any existing structures on the site (if those structures are being demolished or not retained).

23
Q

Different types of Piles?

Construction tech

A
  1. Contiguous Pile
  2. Secant Pile
  3. Sheet Pile
24
Q

What is a Contiguous Pile and pros and cons?

Construction tech

A

A row of bored concrete piles installed with small gaps (typically 50–150 mm) between each pile.

Pros:
1. Low vibration – suitable for urban or sensitive sites.
2. Ideal where minor groundwater ingress is acceptable.

Cons:
1. Not watertight – water can pass through the gaps between piles.
2. Not suitable for high groundwater or permanent basements without secondary waterproofing.

25
What is a secant Pile and pros and cons? | Construction tech
Formed by overlapping bored piles — usually alternating soft (unreinforced) and hard (reinforced) piles. Pros: 1. Watertight (virtually continuous wall) — ideal for high groundwater. 2. Can form part of the permanent basement wall. Cons: 1. More expensive than contiguous walls due to overlap and precision drilling. 2. Slower installation process.
26
What is a sheet Pile and pros and cons? | Construction tech
Thin interlocking steel sheets driven into the ground to form a continuous vertical wall. Pros: 1. Fast installation and easy removal for temporary works. 2. Continuous wall provides good water cut-off (depending on joints). 3. Economical for shallow to medium-depth excavations. Cons: 1. High noise and vibration during installation 2. Limited depth capacity compared to bored systems. 3. Durability concerns (corrosion) for long-term use unless protected.
27
What are some of your firm's weaknesses?
1. Resource Pressure During High Workload Periods 2. Market pressure and skill shortage - G&T struggling to recruit uprising talent
28
Wh
29
What is the document where you can find information about loss and expense? | Contract Practise
Ascertaining Loss and Expense (July 2024)
30
Simply what is a loss and expense? | Contract Practise
Set of tasks that endeavour to calculate the additional costs or losses incurred by one party directly due to a default of the other.
31
What does "to ascertain" mean? | Contract Practise
To ‘find out something for certain or make sure of’.
32
Under a loss and expense, what position should it put you back to? | Contract Practise
The contractor is entitled to recover that loss and expense to put themself back in the financial position that they would otherwise have been in.
33
Different Contract sections under a JCT? | Contract
34
What is the Case law regarding Loss and expense? | Contract Practise
Hadley v Baxendale (1854)
35
What costs do loss and Expense claims account for? | Contract practise
DIrect loss and expense
36
Does loss and expense cliams, allow for consequential loss? | Contract Practise
NO
37
When should a contractor raise a Loss and Expense? | Contract PRactise?
as soon as it has become, or should reasonably have become, apparent to him that the regular progress has been or is likely to be affected;
38
How does the NEC deal with loss and expense differently from a JCT? | Contract PRactise
1. Relevant events and Relevant matters are called compensation events which allocate both time and money 2. The compensation events also have what is known as a condition precedent nature, so failure to notify the compensation event in the prescribed timescale can have serious consequences
39
How does FIDIC deal with Loss and expense comapred to JCT? | Contract Practise
1. Terminology - Loss & Expense vs Cost + Reasonable Profit 2. Notice period - Strict 28 days to Notify + 84 days to submit
40
Cost related to Loss and Expense? | Contract Practise
* failure to give the contractor possession of the site * failure to give the contractor access to and from the site * delays in receiving instructions * opening-up works or testing works that then prove to have been carried out in accordance with the Standard Form Contract * Discrepancies in the contract documents * Disruption caused by works being carried out by the employer * failure by the client/employer to supply goods or materials * instructions relating to variations and expenditure of provisional sums * inaccurate forecasting of works described by approximate quantities * issues relating to The Construction (Design and Management) Regulations 2015 (CDM).
41
What is a global claim? | Contract Practise
Global claims are those where a composite sum or global sum, comprising many differing quantum elements, is asserted by the contractor. Often it takes the formof a simple estimate covering several areas of cost or claim, rather than a more detailed, particularised assessment.
42
What are the 5 main heads of claims | Contract Practise?
1. Prolongation Costs 2. Disruption Costs 3. Loss of Profits 4. Finance charges 5. Head office overheads 6. Preliminary thickening (needs to be proven)
43
What is preliminary thickening? | Contract Practise
The inclusion of additional resources. a. Adding more people on site b. Increase the amount of allocation of people already on the project e.g 20% --> 40%
44
What are some formulas you could use to help with ascetain loss? | Contract Practise
Hudson and Emden Formula
45
What is different ways of risk management? | Risk Managment
1. Monte Carlo Simulation
46
What is the Monte Carlo Simulation? | Risk management
A Monte Carlo Simulation is a probabilistic risk analysis technique used to model uncertainty in project outcomes — such as cost, programme, or cashflow. Instead of using a single value for each risk, it uses ranges (best case, most likely, worst case) and then simulates thousands of possible scenarios to show the overall probability of different outcomes.
47
What does VRF stand for? | M&E
Variable Refridgernet flow
48
What is more expensive FCU or VRF systems and why? | M&E
1. pipework is cheaper 2. VRF is more smart and more control variability - FCU are more basic, either 2 pipe or 4 pipe.
49
When would you use a VRF system? | M&E
1. When there is no central plant room 2.