How were ground conditions exluded from the contract?
Risk excluded from the Contractor’s Proposals.
How did the actual cost compare to the estimate
An addition £23k for an extended 2 weeeks prelims, more accurate surveys
How did the actual programme compare to the estimate
An additional 2 weeks
: 1 week based on 28 days from validation
: 1 week based on GPR
Why does the orange boundary within the drawing not go up to the gas main?
Simply a sketch, the orange line should extend up to 1.5m away from the plots.
Explain the NMA timeline periods
Necessary to make ammendment to already approved a minor change that doesn’t breach any conditions of the original consent.
Made 28 days from validation.
Amends the exiting permission.
S96A
What other planning application routes are availble?
Full planning application is timely anmd requires a pre-application consultation.
MMA Minor Material Amendment: S73 requires a consulation with neighbours and takes up to 8 weeks.
What are the associated timelines and risk with a S73 and MMA?
Up to 8 weeks for re-approval and consultation
What are the associated timelines and risk with a full planning application?
Up to 6 months
- Pre-application
- Design Development
- Submission and validation
- Determination period
Did the utilities company have any responsibility?
No - disclaimer on the drawings saying for information only not to be relied on.
How did the utilities company access the utilities?
Statutory wayleave
What’s the difference between a wayleave & easement?
Easements are a long term contractual agreement
Wayleaves are more flexible where the land owner is paid a compensation but the utuilities company has 24/7 access.
Pre-contract: how did you prepare the Employer’s requirements so close to the contract being signed?
Where there were differences between the CPS & ERs, I ammended the ERS.
What takes precedence, ERs or CPs?
CPS
Why was the project negotiated?
What were other options available?
Negotiation as long term partnerships, my involvement began after this.
Tendering for more contractors, framework of approved contractors for a more competetitive price.
Risk Register review: pre contract risks
Low cost per m2 - financial viability of the scheme being completed.
Agreement of contract documents
Risk Register review: post contract risks
Social: Neighbourly matters
Legal: Planning pre-occupation conditions
Technical: drawing clashes
Economic: Finance
Programme: Delays, material / labour etc
Who updated the programme? You or the contractor?
The contractor has a main works programme
I created an overall project programme with key milestones.
Prepared the JCT D&B contract - what was included within the documents.
Post contract Clause 5.1
What is this clause definition?
Definition of changes
- the addition, omission of substitution of any work
What is a ‘change’
An addition, ommission or alteration to the original scope of works
What is an example of the change?
Workmanship, programme, materials
Who instructed the change?
I did as the PM under clause 3.5 Employer’s Instructions.
you noted the contractor sought guidance on how to proceed? Would this be guidance or an instruction? Why?
Instruction is the formal notice under the contract
Guidance was advice, recommendation or best practice, once reviewed it became a formal instruction
Where was the gas main going? Did it not continue into section 5?
The gas main did not obstruct S5, it rejoined back into the road following the utilitiy drawing