Level 2 Contract Administration Flashcards

(27 cards)

1
Q

What is the PC Cert and what does is mean?

A

Practical Completion when the building has reached beneficial occupancy.
Transfers liability insurance over to the employer.
Defects period commences
Retention released 50 %
LADS no longer applicable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is a notice of of completion of making good issued and what does it mean?

A

Issued at the end of the defect period once satisfied all defects are closed out.
Releases the final 50% of retention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a non-completion notice for and what does it allow?

A

Issued when an EOT is not granted and the completion date is missed, allowing for the client to claim Liquidated Damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are Relevant Events and what do they allow?

A

Allow for Time Only!
Where a delay occurs impacting on the completion date, entitles the contractor to apply for an extension of time.
Must write to the EA as soon as reasonably apparent.
Usually written in the contract
- Variations
- Failure to provide information
- Changes in statutory requirements
- Adverse weather

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What clause is Relevant Events?

A

2.26 Under Adjustment of Completion Dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are relevant matters and what do they allow?

A

Allows for direct loss and expense to be claimed!
- Failure to give the contractor possession of the site
- Delays in receiving instructions
- Opening up and testing which is in accordance
- Instructions relating to variations and expenditure of provisional sums.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What clause is Relevant Matters?

A

4.21 Under Loss and Expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Instructions - how to check market conditions on materials?

A

Spons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Liquidated Damages?

A

Set out in contract particulars, the cost lost per unit per week if the completion date is not met, meaning the client can claim for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Partial Possession

A

Allows for posession of part of the site - not in the contract!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Section Completion

A

Allows for possession of the site - written within the contract with own completion dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Contract Administrator’s responsibilities

A
  • Required under traditional, exists at contract execution
  • Independent role
  • Manage information and record keeping, site inspections, attending meetings, reporting and issuing instructions and notices under the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Employer’s Agent

A

Exists under Design & Build
- Act on bhealf of the client
- Experience, competence and technical knowleddge to support the client
- Preparing ERs
- PEP
- Tendering process
- Contract docs
- Project controls
- Chairing progress meeting and minutes
- Monitoring project finance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contractual Procedures

A

Payment
PC - Insurances transfer, 50% retention release, DLP commences
Non Completion - LADS can be levied
EOT - Extending Completion Date
Time @ Large - completion date missed and no EOT. Contractor entitled to complete works within reasonable time risking the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Frederick Road Responsibilities

A

Assisted on valuations and issued payment notices.
Issuing change instructions, reviewing agains SPONS / referring with QS to ensure correct prices.
Attaching any relevant info to the instruction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Assessing Extension of Time

A
  1. Understand the Relevant Event (exceptionally adverse weather, variations, instructions)
  2. Notices must be issued as soon as reasonably apparant
  3. JCT EA must respond within 8 weeks rather than 12 (JCT 2024)
  4. EOT issued for the section
17
Q

EOT Delay Analysis

A
  1. Overview of the facts: all evidence and emails, minutes etc.
  2. Understand the timeline of events
  3. Compare actual v planned progress
  4. Critical path analysis: software showingn how the CP is delayed and issuign a formal EOT document.
18
Q

Ascertaining Loss & Expense

A
  1. Claim must be made as soon as reasonably apparant
  2. Restricted to direct loss and expense incurred by the contractor.
  3. Relevant information to be provided to support the claim. (emails, invoices, payments)
  4. Prolongation of prelims ( site set up costs & additional charges)
  5. Disruption of labour (attendance registers)
  6. The measured mile (comparing progress against an unaffected section).
  7. Aboritve materialcs, double handling them.
  8. Overheads (time diaries)
19
Q

Park Farm S106?

A

Planning obligation / agreement for the developer to provide affordable housing.

20
Q

Golden Brick Notices

A

Used for Housing Associations to certify the use of residential buildings rather than land. There is no tax contribution.
HMRC two courses of brick above DPC.
I did not provide tax advice, but confirmed when the works completed the required stage.

21
Q

Sheldon Street LADS

A

Different LAD schedules within the contract.
Time X Rate = Total.

Paid for as a debt

22
Q

Roles of the CA under JCT

A

Responsible for adminstering the contract

  • Determining EOT
  • Reviewing L&E
  • PC Certs
  • Issuing instructions
  • Aministring change
  • Interim payment notice
23
Q

Can you issue PC more than once?

A

No and it can’t be recinded

24
Q

What is nomination?

A

Selection of a particular subcontracot to complete the works or supply.
Often used when there is a long lead in time with the employer placing orders and prevents delays on sites.

25
How are nominated subcontractorts paid?
Seperately via the main contract.
26
Whats the difference between statutory provisions and Contract provisions?
S: set out by law and must be complied with C: Only apply to specific projects.
27
How are LADs calculated?
genuine pre-estimate of the employer's likely costs, such as loss of revenue or rental income,