What is the PC Cert and what does is mean?
Practical Completion when the building has reached beneficial occupancy.
Transfers liability insurance over to the employer.
Defects period commences
Retention released 50 %
LADS no longer applicable
When is a notice of of completion of making good issued and what does it mean?
Issued at the end of the defect period once satisfied all defects are closed out.
Releases the final 50% of retention.
What is a non-completion notice for and what does it allow?
Issued when an EOT is not granted and the completion date is missed, allowing for the client to claim Liquidated Damages.
What are Relevant Events and what do they allow?
Allow for Time Only!
Where a delay occurs impacting on the completion date, entitles the contractor to apply for an extension of time.
Must write to the EA as soon as reasonably apparent.
Usually written in the contract
- Variations
- Failure to provide information
- Changes in statutory requirements
- Adverse weather
What clause is Relevant Events?
2.26 Under Adjustment of Completion Dates
What are relevant matters and what do they allow?
Allows for direct loss and expense to be claimed!
- Failure to give the contractor possession of the site
- Delays in receiving instructions
- Opening up and testing which is in accordance
- Instructions relating to variations and expenditure of provisional sums.
What clause is Relevant Matters?
4.21 Under Loss and Expense
Instructions - how to check market conditions on materials?
Spons
What are Liquidated Damages?
Set out in contract particulars, the cost lost per unit per week if the completion date is not met, meaning the client can claim for.
Partial Possession
Allows for posession of part of the site - not in the contract!
Section Completion
Allows for possession of the site - written within the contract with own completion dates.
Contract Administrator’s responsibilities
Employer’s Agent
Exists under Design & Build
- Act on bhealf of the client
- Experience, competence and technical knowleddge to support the client
- Preparing ERs
- PEP
- Tendering process
- Contract docs
- Project controls
- Chairing progress meeting and minutes
- Monitoring project finance.
Contractual Procedures
Payment
PC - Insurances transfer, 50% retention release, DLP commences
Non Completion - LADS can be levied
EOT - Extending Completion Date
Time @ Large - completion date missed and no EOT. Contractor entitled to complete works within reasonable time risking the client.
Frederick Road Responsibilities
Assisted on valuations and issued payment notices.
Issuing change instructions, reviewing agains SPONS / referring with QS to ensure correct prices.
Attaching any relevant info to the instruction.
Assessing Extension of Time
EOT Delay Analysis
Ascertaining Loss & Expense
Park Farm S106?
Planning obligation / agreement for the developer to provide affordable housing.
Golden Brick Notices
Used for Housing Associations to certify the use of residential buildings rather than land. There is no tax contribution.
HMRC two courses of brick above DPC.
I did not provide tax advice, but confirmed when the works completed the required stage.
Sheldon Street LADS
Different LAD schedules within the contract.
Time X Rate = Total.
Paid for as a debt
Roles of the CA under JCT
Responsible for adminstering the contract
Can you issue PC more than once?
No and it can’t be recinded
What is nomination?
Selection of a particular subcontracot to complete the works or supply.
Often used when there is a long lead in time with the employer placing orders and prevents delays on sites.