Level 3 Programming & Planning Flashcards

(46 cards)

1
Q

What is a programme?

A

Sequence of events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does a project programme identify?

A
  • The overall start date
  • The overall completion date
  • Start date for each activity
  • Completion date for each activity
  • Amount of float each activity
  • The critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefits of Programmes

A

a) plan activities
b) monitor progress
c) manage resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Types of programme

A
  • Contractors Master Programme Schedule and sequence of construction activities
  • Clients overall programme: everything from appointment through to completion of the project
  • Design Programme: describes the sequence of design tasks from the process of design from inception to technical completion.
  • Information release schedule: dates which information needs to be released by the design team to avoid any delays
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Consideration when preparing a programme

A

Items with a long lead in
Pre-contract works
Pre-fab elements
Works outside the main contract
Relationships with other projects
CDM Planning period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Gantt chart?

A

A way of displaying programme, through a combination of bars each relating to an activity of a specified duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a flow diagram?

A

A graphical representation of a process of steps/sequences required to achieve an end goals. Helps the team to understand the different process and relationships between activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is an activity schedule?

A

A list of activities which outlines the works required to complete a project. Used for simple projects with few activities, usually presented as a gantt chart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Float?

A

The amount of time an activity can be delayed without delaying the subsequent activity of critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Types of float: Time Float?

A

Time an activity can be delayed without delaying the planned completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Time Risk Allowance?

A

Duration allowed in each activity by the contractor to account for the risk of not completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Critical Path?

A

The longest sequence of activities in a project which must be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Programme Acceleration?

A

Moving a project closer to completion date at a faster pace than planned, to either complete the works prior to original completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Risks of Programme Acceleration?

A
  • Acceleration activities don’t impact the critical path.
  • Shift work can lead to inconsistencies in the quality of work
  • Night/ weekend work can be expensive due to enhanced payment
  • Imbalance between supervision, labour, plant & materials can affect productivity
  • More resources mean more welfare, higher risk of H&s.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When developing a master programme for a client, what should be considered?

A
  • What is your governance process and timings, key meetings
  • When do you want to complete?
  • What is their governance process and timings, key meetings etc?
  • What procurement route would you consider?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EOT Analysis Types

A

Planned Impact
Time Impact
Time slice window analysis
Collapsed as built analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

EOT: Planned impact

A

Introducing a delay even sub-network into the baseline programme, needs to be logic linked.

Y: Simple, cheap
N: Doesn’t consider actual progress and changes to the original programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

EOT: Time Impact Analysis

A

Introducing a delay event sub-network into updated programme, needs to be logic linked
Y: Simple/inexpensive
N: Doesn’t capture eventual delay as subsequent project progress is not considered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

EOT: Time slice

A

Updated programme, progress of works divided into time slices, actual critical path.
Y: More sophisticated view on delay, removes complexities of reviewing project as a whole
N: Only done retrospectively, more specialist analysis

20
Q

PERT?

A

Programme, Evaluation, Review Technique: Creating 3 estimates for the duration of a project.

21
Q

What is dependency in programme?

A

Where a task or activity is reliant on another task/activity to complete before it can start?

22
Q

How to get from one RIBA stage to the next?

A

Stage gate approvals: client sign off key deliverables within the stage

23
Q

Types of logic links within a programme

A
  • Start to start
  • Start to finish
  • Finish to start
  • Finish to finish
24
Q

What is the CDM Planning Period?

A

An amount of time given to the contractor, with the intention of allowing contractors to asses H&S issues and plan their works before construction commences

25
How long is the CDM Planning Period?
Not specified, it should be proportional to the size and complexity of the project
26
Difference between total float & free float?
Total: amount of time an acitivty can be delayed before affecting the end date Free: the amount of time an activity can be delayed before affecting a subsequent activity.
27
How to create a programme?
- Scope of programme - Work breakdown structure - Consult wider team - Add risk and opportunity - Run anlalysis of scenarios - Identify the CP - Identify assumption
28
How to show progress on a programme?
- Drop line - % complete metrics - Jagged drop line
29
Time at large?
When the EOT mechanism is broken and unenforceable meaning completion is effectively whenever it is, removes the obligation to pay LADS.
30
Some alternatives to a Gantt Chart?
- Network diagrams - WBS - Sprint cycles
31
Difference between resource levelling and resource smoothing
Both are used to avoid peaks and troughs Levelling: when resources are constrained, what is the programme going to be? Smoothing: When time is constrained, can resources be smoothed out to achieve the end date? i.e delay some tasks to get the CP done.
32
Benefits of using programmes?
- Manage resources - Monitor progress - Plan activities
33
what is contractor's main programme?
breakdown of work elements
34
Information release schedules?
Used prior to handover to manage expectation of commissioning information to be delivered.
35
What is a Gantt chart?
A visual display of a programme showing acitivities and durations using bars.
36
What is float?
Allowance an activity can be delayed without affecting the overall completion date.
37
Ashmere Ensuite removal
Understanding of the latest date for an instruction. Working back from events. 1st fix installation dates. Consider lead in times. Any delay from an instruction or abortive works would be an affect on the client.
38
Frederick Road progress reviews
Reviewing as built against planned works on a drop down programme.
39
Hatcham Gardens Tender Programme Key milestones
Once the process started a created a timeline - ITT - Review - Report - Contract Award - SOS
40
Somerleyton Road Master Programme
Client gave me a target date and I advised if it was realistic. Working back from the date and collating durations from procurement professionals and expertise from my senior colleagues, directors included. * soft market testing * tender process & procurement * slection questionnaire * Negotiation * Recommendation Report * Preferred bidder Overlapping activities included residennt engagement and risk mitigation.
41
Absence / resource schedule
Key to understand if key decision makers were available for the required time. Any delays to decision making would affect the contract completion date.
42
Broadwater Farm 5 phase project programme (250 units)
Plannign decision recieved I created an overall programme, during the PCSA and market testing. 5 Phases from planning information. - Contract offer -VFM - Contract award - Planning pre-commence - Risk - Mobilastionp - SOS - Construction phase plan - Testing and commision - Snag / Quality - PC - Defects
43
Overlapping activies on Broadwater farm
- Risk management - Phases - Planning discharges - Resident Enagemnent
44
How did you use the programme to manage risk?
Tracking progress V programme to identify any areas of delay.
45
How did you advise on acceleration options?
I identified areas of activities which could be conducted simultaneosly.
46
What is a work breakdown structure
A breakdown of project milestones in manageable components