What is the role of a contract administrator?
To act independently and objectively in administering the contract, ensuring compliance with its terms and managing communications between parties.
Why must a contract administrator remain impartial?
Because they are responsible for fair administration of the contract, even though they are employed by the client.
What is the RICS Guidance Note for contract administration?
It provides best practice advice on the duties and responsibilities of contract administrators.
What are the main types of JCT contracts?
Minor Works, Intermediate, and Design & Build, each suited to different project sizes and complexities.
When is a JCT Intermediate Building Contract appropriate?
For projects of moderate complexity where some design input is required from the contractor.
What is the purpose of contract instructions?
To formally instruct the contractor to carry out variations or additional works.
What is a provisional sum?
An allowance in the contract for work that is not fully defined at the time of tender.
What is a payment certificate?
A document issued by the contract administrator certifying the amount due to the contractor for completed work.
What is practical completion?
The stage when the works are complete except for minor defects, allowing the client to take possession.
What is the defects liability period?
A set period after practical completion during which the contractor must rectify any defects.
What is a certificate of making good defects?
Issued at the end of the defects liability period to confirm all defects have been rectified.
What is the purpose of progress meetings?
To review progress, address issues, and ensure all parties are informed and coordinated.
What is the difference between JCT and NEC contracts?
JCT is more prescriptive and traditional, while NEC is more collaborative and flexible.
What is a contract programme?
A schedule showing the planned sequence and timing of construction activities.
What is a formal meeting agenda?
A document outlining topics to be discussed at a meeting, issued in advance to attendees.
Why are meeting minutes important?
They provide a record of discussions, decisions, and actions agreed during meetings.
What is a variation?
A change to the works agreed after the contract is signed.
What is the importance of issuing instructions promptly?
To avoid delays and disputes, and to ensure the contractor has clear direction.
What is a final account?
The agreed statement of the total amount due to the contractor at the end of the project.
What is the role of the contract administrator in dispute resolution?
To provide impartial advice, maintain records, and facilitate resolution in accordance with the contract.
What is the role of a Contract Administrator?
The Contract Administrator is the individual responsible for administering the construction contract.
Contract administrators are appointed by the client, but when certifying or giving an assessment or decision, they should act honestly and reasonably, and their decisions are open to challenge via the dispute resolution procedure unless the contract makes their decisions final and conclusive.
What are the key differences between NEC and JCT?
Time – A programme is a key document within NEC and is used as a tool for assessing change against and must be revised necessary. Deductions are made if a contractor fails to submit first programme. In JCT contractor must submit a programme as soon as possible after contract is executed but there are no requirements as to what this should include and no requirement to submit revised programmes.
Cost – JCT splits up time and cost separately and deals with them after the change occurs whereas NEC deals with effect of time and cost together through the Compensation Event process. In JCT variations/claims are dealt with in a reactive manner, in NEC compensation events are dealt with in a proactive manner.
Can you explain the JCT valuation procedure?
The Contract includes clauses that detail:
- The valuation methodCriteria under which Interim
- Payments will be made
- Payment timings
- Administrative rules to which those undertaking the valuation should adhere.
- The valuation is the pre-cursor to the issue of the interim certificate, which in turn allows the interim payment to be made.
- Contractor raises Valuation (application) 7 days before the due date.
- The CA or QS has 5 days to assess the Valuation
- The CA or QS must raise the Payment Notice no later than 5 days after the Valuation due date.
- Payless Notice must be raised no later than 5 days before the final date for payment.
- Final Date for Payment – 14 or 28 days from the due date (depends on what was agreed/stated in the contract prelims).
Can you explain the Payless Notice procedure?
The client must issue a payment notice within five days of the date for payment, even if no amount is due. Alternatively, if the contract allows, the contractor may make an application for payment, which is treated as if it is the payment notice.
The client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
The notified sum is payable by the final date for payment.
If the client (or specified person) fails to issue a payment notice, the contractor may issue a default payment notice. The final date for payment is extended by the period between when the client should have issued a payment notice and when the contractor issued the default payment notice. If the client does not issue a pay less notice, they must pay the amount in the default payment notice.