What are the main types of building contracts used in the UK?
JCT (Joint Contracts Tribunal), NEC (New Engineering Contract), and others such as PPC2000 and GC/Works.
When should a JCT Intermediate Building Contract be used?
For projects of moderate complexity where some design input is required from the contractor.
What is the purpose of contract particulars?
To set out project-specific details such as parties, contract sum, and key dates.
What is a schedule of works?
A document detailing the scope and sequence of construction activities.
What is a contract instruction?
A formal direction from the contract administrator to the contractor to carry out a variation or additional work.
What is a variation under a building contract?
A change to the works agreed after the contract has been signed.
What is an interim payment application?
A request from the contractor for payment for work completed to date.
What is a valuation in a JCT contract?
The process of assessing the value of work completed for payment purposes.
What is the purpose of a retention in building contracts?
To withhold a portion of payment until defects are rectified after completion.
What is a defects liability period?
A set period after practical completion during which the contractor must rectify defects.
What is the difference between JCT and NEC contracts?
JCT is more prescriptive and traditional; NEC is more flexible and promotes collaboration.
What is a contract programme?
A schedule setting out the planned sequence and timing of works.
What is a certificate of practical completion?
A document confirming that the works are substantially complete and fit for occupation.
What is a final account?
The agreed statement of the total amount due under the contract.
What is a liquidated damages clause?
A provision specifying the amount payable by the contractor for late completion.
What is the purpose of insurance in building contracts?
To protect against risks such as damage, injury, or loss during construction.
What is a direct loss and/or expense claim?
A claim by the contractor for additional costs incurred due to delays or changes.
What is the role of the contract administrator?
To manage the contract impartially, issue instructions, and certify payments.
What is a notice period in contract practice?
The required time for giving formal notice of certain events or actions under the contract.
What is the significance of contract records?
They provide an audit trail and evidence in case of disputes.
Name 3 relevant Events in JCT contract?
In a JCT contract, a Relevant Event refers to a circumstance or occurrence that may entitle the contractor to an extension of time for completing the works. It does not automatically entitle the contractor to additional payment—that would fall under a Relevant Matter.
Here are some common Relevant Events under JCT contracts:
What is a relevant matter in a JCT contract?
In a JCT contract, a Relevant Matter refers to a situation that may entitle the contractor to loss and expense compensation—typically under Clause 4.24 of the JCT Design and Build 2016, for example.
These are different from Relevant Events, which relate to time extensions. Relevant Matters deal with financial claims due to disruption or additional costs caused by the employer or other specified circumstances.
Common Relevant Matters include:
What are the main types of procurement route used in both private and public sectors?
Traditional
Single-stage design and build
Two-stage design and build
Management contract
PFI
How do you select the most appropriate contract for a construction project?
Based on the projects scale and complexity