Contract Practice - Level 1 Flashcards

(34 cards)

1
Q

What are the main types of building contracts used in the UK?

A

JCT (Joint Contracts Tribunal), NEC (New Engineering Contract), and others such as PPC2000 and GC/Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When should a JCT Intermediate Building Contract be used?

A

For projects of moderate complexity where some design input is required from the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of contract particulars?

A

To set out project-specific details such as parties, contract sum, and key dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a schedule of works?

A

A document detailing the scope and sequence of construction activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a contract instruction?

A

A formal direction from the contract administrator to the contractor to carry out a variation or additional work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a variation under a building contract?

A

A change to the works agreed after the contract has been signed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an interim payment application?

A

A request from the contractor for payment for work completed to date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a valuation in a JCT contract?

A

The process of assessing the value of work completed for payment purposes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of a retention in building contracts?

A

To withhold a portion of payment until defects are rectified after completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a defects liability period?

A

A set period after practical completion during which the contractor must rectify defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between JCT and NEC contracts?

A

JCT is more prescriptive and traditional; NEC is more flexible and promotes collaboration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a contract programme?

A

A schedule setting out the planned sequence and timing of works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a certificate of practical completion?

A

A document confirming that the works are substantially complete and fit for occupation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a final account?

A

The agreed statement of the total amount due under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a liquidated damages clause?

A

A provision specifying the amount payable by the contractor for late completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of insurance in building contracts?

A

To protect against risks such as damage, injury, or loss during construction.

17
Q

What is a direct loss and/or expense claim?

A

A claim by the contractor for additional costs incurred due to delays or changes.

18
Q

What is the role of the contract administrator?

A

To manage the contract impartially, issue instructions, and certify payments.

19
Q

What is a notice period in contract practice?

A

The required time for giving formal notice of certain events or actions under the contract.

20
Q

What is the significance of contract records?

A

They provide an audit trail and evidence in case of disputes.

21
Q

Name 3 relevant Events in JCT contract?

A

In a JCT contract, a Relevant Event refers to a circumstance or occurrence that may entitle the contractor to an extension of time for completing the works. It does not automatically entitle the contractor to additional payment—that would fall under a Relevant Matter.
Here are some common Relevant Events under JCT contracts:

  • Variations instructed by the employer.
  • Delay in giving possession of the site.
  • Architect’s instructions or failure to give instructions on time.
22
Q

What is a relevant matter in a JCT contract?

A

In a JCT contract, a Relevant Matter refers to a situation that may entitle the contractor to loss and expense compensation—typically under Clause 4.24 of the JCT Design and Build 2016, for example.
These are different from Relevant Events, which relate to time extensions. Relevant Matters deal with financial claims due to disruption or additional costs caused by the employer or other specified circumstances.
Common Relevant Matters include:

  • Variations to the works instructed by the employer.
  • Failure to give possession of the site on time.
  • Late instructions from the employer or contract administrator.
23
Q

What are the main types of procurement route used in both private and public sectors?

A

Traditional
Single-stage design and build
Two-stage design and build
Management contract
PFI

24
Q

How do you select the most appropriate contract for a construction project?

A

Based on the projects scale and complexity

25
What are the key differences between NEC and JCT?
Time – A programme is a key document within NEC and is used as a tool for assessing change against and must be revised necessary. Deductions are made if a contractor fails to submit first programme. In JCT contractor must submit a programme as soon as possible after contract is executed but there are no requirements as to what this should include and no requirement to submit revised programmes. Cost – JCT splits up time and cost separately and deals with them after the change occurs whereas NEC deals with effect of time and cost together through the Compensation Event process. In JCT variations/claims are dealt with in a reactive manner, in NEC compensation events are dealt with in a proactive manner.
26
Can you name the NEC options?
Option A: Priced contract with activity schedule. Option B: Priced contract with bill of quantities. Option C: Target contract with activity schedule. Option D: Target contract with bill of quantities. Option E: Cost reimbursable contract. Option F: Management contract.
27
Can you list the typcial types of certificates you may use under a JCT Contract?
Interim Payment Certificate – Payment certificate of some kind for the contractor. Certificate of Non-Completion – occurs at end of project when contractor does not achieve PC Practical Completion Certificate – occurs when PC is achieved Certificate of Making good – issued at the end of defects liability confirming contractor has addressed issues. Final Certificate – once final account has been agreed and within 2 months of end of rectification period.
28
Can you explain the contractual mechanisms of sectional completion?
29
Can you explain the Term Front Loading?
This could be a situation / sign where the contractor is claiming for works in advance / not physically carried out on site. This could suggest they are in financial trouble and are advancing their cash flow.
30
What is your understanding of a Parent Company Guarantee (PCG)?
A parent company guarantee (PCG) is a guarantee given by one contracting party's ultimate or intermediate holding company in favour of the other contracting party to secure the performance of that party's obligations under the contract.
31
When would a PCG be used?
In construction, parent companies most commonly give guarantees to bolster the financial credibility of their subsidiary companies.
32
What is a Performance Bond?
A performance bond (or performance security) used in the construction industry is a means of insuring a client against the risk of a contractor failing to fulfil contractual obligations to the client. Performance bonds can also be required from other parties to a construction contract. Whether or not a performance bond is required will depend, in the main, on the perceived financial strength of the party bidding to win a contract, as the most common concern relates to a contractor becoming insolvent before completing the contract.
33
What does the term Time at Large mean?
Construction contracts will usually include a date by which the works described in the contract should be completed. This is generally the date by which practical completion must be certified.
34
What is a collateral warranty?
Collateral warranties are used as a supporting document to a primary contract where an agreement needs to be put in place with a third party outside of the primary contract.