Contract Practice - Level 1 Flashcards

(17 cards)

1
Q

What are the key elements of a legally binding construction contract?

What should it include?

What happens if one of these is missing?

A
  • offer, acceptance, consideration, and an intention to create legal relations.
  • It should clearly define the parties’ rights and obligations, the scope of works, pricing and payment mechanisms, programme requirements, and dispute resolution procedures.
  • Increased uncertainty, implied terms, or reliance on statutory mechanisms.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is it important that a contract clearly defines rights and obligations?

A

Because it establishes who is responsible for what and allocates risk appropriately. Clear obligations reduce ambiguity and protect both parties if disputes arise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the typical payment mechanisms used in construction contracts?

A

Typical payment mechanisms include lump sum, remeasurement, target cost, cost reimbursable, and interim valuations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why include payment and dispute resolution mechanisms?

A

Payment provisions ensure cash flow and compliance with statutory requirements, while dispute resolution procedures provide a structured way to resolve disagreements without immediately resorting to litigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why must dispute resolution procedures be included in contracts?

A

Disputes are a foreseeable risk in construction. Clear procedures provide certainty, support continuity of works, and reduce escalation to costly litigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In what circumstances might NEC be preferred over JCT?

A

NEC may be preferred where collaboration, flexibility, and active contract management are important.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages and limitations of standard forms of contract?

A

Standard forms are well understood, legally tested, and reduce administrative burden. However, they do not fit every project perfectly and may require careful amendment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a letter of intent?

A

A letter of intent allows limited early works to proceed before a full contract is executed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In what circumstances might a client request a letter of intent?

A

Often due to client programme or budget pressure, or to secure resources or supply within in case of scarcity, or to engage a preferred contractor before they become occupied by a different opportunity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the risks of proceeding under a letter of intent?

A

The key risks are unclear scope, capped liability being exceeded, disputes over payment entitlement, and unintentionally creating a binding contract without full protections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is capped liability?

A

Capped liability is a negotiated, contractual limit on the maximum financial responsibility a contractor or consultant faces for damages, breaches, or negligence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What would you do to protect a client if a letter of intent was unavoidable?

A

Good practice would be to limit scope, value, duration, and clearly state intention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What factors influence contract selection?

A

Contract selection is influenced by project scale, complexity, location, risk allocation, client capability, programme certainty, and client objectives. For example, collaborative risk-sharing may suit NEC, whereas more prescriptive risk allocation may suit JCT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does risk appetite affect the choice of contract?

A

A client with low risk appetite may prefer fixed-price arrangements for cost certainty, whereas a client willing to share risk may select collaborative forms like NEC target cost to manage uncertainty more transparently.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the key differences between JCT and NEC contracts?

A

JCT is more prescriptive and risk-allocative, with detailed clauses defining liabilities. NEC is more collaborative and management-focused, using plain language. For example, NEC requires risks to be raised and addressed in real time rather than retrospectively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do client objectives influence the choice of procurement and contract form?

A

Client objectives such as cost certainty, speed, risk appetite, operational continuity, and sustainability directly influence procurement and contract choice; for example, a client prioritising flexibility and business continuity may select NEC with phased handover, while one seeking early cost certainty may prefer a more fixed-price approach.

17
Q

Can you give me an example of where the wrong contract choice can cause problems?

A

Using a lump-sum contract on a poorly surveyed refurbishment can lead to frequent variations, disputes, and cost escalation, as risk priced by the contractor materialises during construction.