Programming and Planning - Level 1 Flashcards

(41 cards)

1
Q

What is the difference between planning and programming?

A

Planning defines what needs to be done, while programming sets out when and in what order it will be done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you tell me some takeaway from the RICS Programming and planning course and how you have applied it?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is planning important in construction projects?

A

Planning is essential to coordinate activities, manage resources, and ensure the project is delivered safely, on time, and within budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do you do if you realise the programme is falling behind?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What risks arise from poor planning?

A
  • Delays
    -cost overruns
  • resource conflicts
  • rework
  • increased project risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a construction programme?

What is the purpose of it?

A
  • A construction programme is a structured plan that sets out the sequence, duration, and dependencies of activities required to deliver a project.
  • To plan, sequence, and manage activities during the construction phase.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the critical path?

how do you identify it?

why is it important?

A
  • the longest sequence of dependent activities that must be completed on schedule for a project to be finished on timed. The path with zero float.
  • It is identified through logic links and duration analysis within the programme.
  • Because any delay to critical activities directly delays the overall project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the difference between critical and non-critical activities?

What happens if a critical activity is delayed?

Can non-critical activities affect the project completion date?

A
  • Critical activities directly affect the completion date, while non-critical activities have float and can be delayed without impacting overall completion.
  • The overall project completion date is delayed.
  • Yes, if their float is used up and they become critical.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is float?

why is it important?

A
  • the extra time available for an activity beyond its planned duration. Or
  • The amount of time an activity can be delayed without affecting the project completion date.
  • It provides flexibility and is a key indicator of programme risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

how is float calculated?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are different types of float?

A
  • Total float (time available without delaying completion)
  • free float (time available without delaying the next activity).
  • in NEC contracts; terminal float (the time between the contractors planned completion and the contractual completion)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what happens if float is used up?

A

The activity becomes critical and any further delay will impact the project completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How can float be eroded during a project?

A

Through delays to preceding activities, changes in scope, poor sequencing, or unplanned constraints or events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

who owns float?

A
  • total float can be owned by the contractor to manage risk but it is often shared and used on a first come first served basis.
  • however, terminal float in nec contracts is owned by the contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between critical path and float?

A

The critical path determines project duration, while float is the flexibility available on non-critical activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Work Breakdown Structure (WBS)?

Why is a WBS useful?

A
  • A WBS is a hierarchical breakdown of the project into smaller, manageable tasks.
  • It helps define scope, organise activities logically, and ensure nothing is overlooked.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What do you mean by logical sequencing?

A

Arranging activities in the correct order based on dependencies and available resources, rather than arbitrary dates.

18
Q

Why is poor sequencing a programme risk?

A

It creates unrealistic assumptions and increases the likelihood of delay or rework.

19
Q

What are dependencies in a programme?

How do dependencies affect programme reliability?

A
  • Relationships between activities that determine the order in which they must be completed.
  • If dependencies are not correctly identified, delays may not be visible until it’s too late, undermining the reliability of the programme.
20
Q

What types of dependencies exist?

A
  • Finish-to-start (most common)
  • start-to-start
  • finish-to-finish
  • start-to-finish.
21
Q

What are typical constraints that affect sequencing?

A

Typical constraints include site access and logistics, material lead times, labour and equipment resource, time and cost, external constraints such as weather, safety and quality controls.

22
Q

What is a Gantt chart?

what are the advanatages and limitations of gantt charts?

A
  • A visual representation of a programme showing activities against time.
  • Gantt charts are easy to understand and useful for communicating programme information.
  • however they can mask poor logic if not properly linked and should not be relied on without understanding dependencies and float.
23
Q

What other programming tools are available?

What are other methods to visualise the programme?

A

Tools like Microsoft Project visualise the programme in a linked bar chard method. But there is also;

  • bar chart diagrams
  • Network diagrams or arrow diagrams
  • precedence diagrams.
24
Q

How have you used Microsoft Project?

A

I have used Microsoft Project at a basic level to identify critical paths, monitor progress of tasks on the critical path and understand and establish the length of projects.

25
How do you monitor progress against a programme?
By comparing actual progress against the baseline and reviewing key milestones, progress updates, and review of critical path movement with the contractor.
26
What is the difference between baseline and actual performance? Why is baseline comparison important?
- The baseline is the planned programme; actual performance shows real progress. - Comparing the two highlights variance and emerging risk. It allows identification of delays and supports corrective action.
27
What is milestone tracking, and why is it useful?
Monitoring key points or completion points rather than every activity. - It is useful for monitoring progress, identifying slippage early, and supporting governance reporting.
28
How do you assess whether a programme is realistic?
By testing logic, durations, lead times, dependencies - alignment with known constraints and assurance processes. - input from relevant stakeholders.
29
what should be included in an NEC Programme? what is the required detail for a programme?
- key dates; start dates, access dates, sectional completions, planned completion, completion dates - order and timing of contractor activities to complet the works - order and timining of activities by clients or other as agreed with them - float and time risks allowances - programme narrative / statements of how the work will be carried out
30
What are the reasons for a project manager to not accept a programme?
- the contractors plan are not practicable - it does not show the required information - it does not repesent the plans relaistically - it does not comply with the scope.
31
what is the programme narrative? what does it include?
it's the statement of how the contract plans to carry out the works includes; - sequence of activities - resources and equipment required - critical path - time risk allowances and assumptions - key dates
32
What factors should be considered when developing a programme?
- Scope - resources - sequencing - lead times - risks and external constraints.
33
How do you account for uncertainty in a programme?
****- By including contingency, reviewing risks, and regularly updating the programme.
34
Why are lead times important in programming? what is their impact?
- Because procurement and manufacture often drive the critical path, particularly for specialist equipment. - They can delay activities and must be factored in to ensure realistic sequencing.
35
How do you use programmes to support decision-making rather than just reporting?
By using them to test scenarios, assess impacts of change, identify emerging critical risks, and inform discussions on re-sequencing or re-phasing rather than simply recording progress.
36
What risks arise if lead times are underestimated?
Delays, rushed decisions, increased cost due to impact on programme.
37
What does RICS guidance say about assessing programme feasibility?
RICS guidance emphasises testing logic, durations, lead times, dependencies, and external constraints to ensure programmes are realistic and achievable.
38
How would you develop a basic construction programme? How would you identify the critical path?
1- establishing scope 2- breaking it into tasks 3- sequencing activities 4 - assigning durations 5- identifying dependencies, 6 -sharing with stakeholders for feedback. - By analysing the sequence of activities and identifying the longest path with no float.
39
How would you update a programme during a project?
By recording actual progress, comparing it to the baseline, and revising forecasts as needed.
40
What is the difference between a programme and a schedule of works?
A programme is a comprehensive, time-based plan detailing the sequence of tasks, dependencies, resources, and milestones to complete a project, often visualized as a Gantt chart. A schedule is generally a more focused list of activities, dates, and deadlines, often forming a subset of the overall programme.
41