Programming and Planning - Level 3 Flashcards

(52 cards)

1
Q

What was your role in managing the overall programme rather than individual projects?

A
  • I was responsible for overseeing the master delivery programme and ensuring we re hitting the key milestone for every project
  • advising the client on how individual project delays affected overall objectives, particularly ensuring completion ahead of high-profile events.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you identify that the programme was no longer achievable?

A

Through monitoring key milestones,

I identified that the railing works were forecast to complete beyond the required deadline due to planning delays,

this reduced the available delivery window.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What made this a programme-level issue rather than a project-level issue?

A
  • Because the delay affected the overall objective of preparing the site for high-profile events, not just the completion of a single work package.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you assess the impact of the delay on the wider programme?

A
  • I reviewed key milestones,
  • identifying that the railing works would not complete in time and
  • posed a risk to security readiness for the events.
  • undermined all other projects completed on time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you determine that railing works were no longer recoverable?

A

I tested acceleration options with the contractor and concluded that constraints such as planning restrictions, labour availability, and site limitations meant recovery within the required timeframe was not feasible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What programme management techniques did you use to analyse recovery options?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Did the delay to the planning permissions not affect all of the projects
equally?

A

yes, it did but there was available float in and opportunity to suitably accelerate the other programmes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What options did you consider to recover the programme?

A
  • Additional labour,
  • out-of-hours working, and
  • reallocating some labour from other projects.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you assess the viability of acceleration measures?

A
  • By considering cost,
  • practical constraints
  • the extent to which each option would meaningfully reduce programme duration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why was additional labour not effective in this case?

A

Due to site constraints and personnel vetting requirements,

it limited who and how quickly additional resources could be deployed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why were out-of-hours works not feasible?

A

Because local authority restrictions limited noisy activities after 6pm on weekdays and 1pm on weekends so there was limited extra time

  • this is particularly relevant because the groundworks required would be noisy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why did reallocating labour introduce further risk?

A

It would have impacted higher-priority works, particularly the dome refurbishment, which was critical to the programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did you prioritise between the different projects?

A

I considered each project against the client’s key objective of ensuring the site was ready and secure for the events.

  • I considered the impact of not completing a project, the dome would be highly visible, part of the event, also not completing it would mean the building did not have a suitable roof over the main lobby
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why was the dome refurbishment prioritised over railing works?

A

Because it was critical to the event and had less flexibility in sequencing compared to the railing works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you determine what was critical to the client’s objectives?

A
  • Through regular engagement with stakeholders
  • understanding the operational requirements for the events.
  • knowing the key intended outcomes for the projects (Statement of Need)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did you identify the Intruder Detection System as an alternative solution?

A
  • Once I reflected back to the underlying objective—perimeter security— I realised that we could try achieving this with the IDS project.
  • I then began liasing withe the project manager for that to test this option.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Why was this a better solution than accelerating railing works?

A

It provided a cost-efficient and deliverable solution within the required timeframe, whereas acceleration would not achieve programme recovery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What factors did you consider when expanding the scope of another project?

A
  • Feasibility
  • cost
  • delivery timeframe
  • alignment with the client’s objectives.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What risks were you managing through your recommendation?

A
  • Programme delay
  • failure to meet security requirements
  • disruption during event
  • reputational risk associated with high-profile events.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How did your approach reduce programme and reputational risk?

A

it provided a deliverable solution to improving perimiter security within the timeframe and avoiding reliance on unachievable programme recovery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What risks would have arisen if you had continued with the original plan?

A
  • Failure to complete works on time
  • increased costs
  • reputational damage.
22
Q

How did you present your recommendation to senior stakeholders?

A
  • During a formal update meeting;
  • i shared the issue i identified
  • the options i looked at withe the contractors
  • shared my advised approached and the risk and benefits before asking for their approval.
23
Q

How did you ensure your advice was understood and accepted?

A

clearly linking the recommendation to the client’s objectives

and demonstrating why alternatives were not viable.

24
Q

How did you manage differing stakeholder priorities?

A

By focusing discussions on shared objectives, particularly security and event readiness.

25
What steps did you take after the decision was made?
- i comfirmed with the establishement when would be a suitable date after the events to start railing construction - i instructed the railings team not to go to market and mobilise for construction phase task this year but rephase it to match the suitable date. (planning would be valid for three years). - informed the project management office so that this could be reflected in the future project forecasts - i instructed the IDS team to extend the scope and of the ids project to include the railings - set up a change management meeting to confirm this change was approved formally updated the milestones on the master delivery programme and ensure they reflected with the project managers programmes - shared the update at the next team update meeting and recorded the minutes for everyone's reference.
26
How did you update and communicate the master programme?
- i liased with the relevant project managers during my project management catch-up meeting i ensure that the key days on their programme for the revised programmes mirrorerd the key dates and milestones in my master delivery programme and client portal - this was then communicated visually as the key milestones adjusted new net forecast dates during a stakeholder monthly meeting.
27
How did you ensure contractors aligned with the revised approach?
- Through revised programme documentation - coordination and agreement on the future plans - emphashised the project goals and the delivery timeline before the events
28
How did the cyberattack impact programme certainty?
- not decision date was given for a while and then when it was given it was 20 weeks laster than expected. - not having the decision and having it delayed meant there was no cenrtainty to based the programme timelines on.
29
How do you manage programmes with external dependencies outside your control?
- i regularly monitor progress to identify emerging risks as early as possible. - begin exploring and developing contingegy options or assessing how to mitigate risks before they can fully materialise - enough and correct allowance for periods that sit outside my control.
30
How do you plan for events like planning delays?
- Usually by building flexibility into the programme, however, this level of delay used up all the time allowance assigned to it. - developing and maintaining alternative delivery strategies.
31
How do you decide when to stop trying to recover a programme and instead re-plan?
When recovery options are no longer viable or proportionate, and continuing would introduce greater risk.
32
How do you balance cost, programme, and risk when advising the client?
By assessing each option holistically and recommending the approach that best meets the client’s objectives.
33
How do you ensure your recommendation represents best value rather than just quickest delivery?
considering long-term effectiveness and cost efficiency, not just speed. - in this instance speed was obviosuly a benefit as we were limited for delivery time, but if a solution that was more expensiveor took longer delivered more fully the for the client's objective, I would have investigated it and potentially proposed it.
34
What would you have done if the client insisted on completing the railing works before the event?
- I would clearly outline the risks and limitations - show that the option was explored but it was not viable - i would emphasise that it could not be completed ahead of the event - if they continue to insist, I would ensure the decision was formally documented.
35
How do you ensure one project change does not negatively impact the wider programme?
- by meeting with the various project manager to ensure that the re arent any negagative dependencies that could impact other projects later on. - testing it by putting it on the master programme to see it if works alongside the other projects.
36
What lessons did you take from this situation?
- The importance of flexibility and focusing on outcomes rather than fixed solutions. - seeking planning approval as early as possible where possible
37
How would you improve programme resilience on future projects?
- by developing contingency strategies and alternative solutions to reach outcomes much earlier in the project. - ensure that there is more time available for citicatal activities like planning periods
38
How could earlier planning have reduced this issue?
- planning for potential planning approval risks and delays earlier and allowing greater programme float, could have help this, - however, the delay reasons were extraordinary so the extra tiem allowance may be unrealistic in most circumstances
39
Was your solution actually a programme solution or just scope change?
- It was both, but primarily a programme-led solution. While it involved a change in scope, the decision was driven by the need to achieve the client’s programme objective. - I employed programme recovery methods to test accellerating the construction of the railing upgrades. - when programming techniques did not achive the necessary betterment, i looked at the wider mater delivery programme and considered the original objectves that were established. - This approach reflects programme-level thinking, where the focus is on delivering the overall objective rather than strictly adhering to the original scope.
40
How did you ensure this didn’t create risk elsewhere?
- I liased openly and honestly with the project manager for the IDS project - i didn't just ask for the cost but also asked for them to provide a feasibility assessment, which was a forecast of dates under this framework contract, to see if the IDS on the railigns would be done on time and without affecting the other aspects of that project. - also ensured the railing works were re-phased in a controlled way, so they did not create future clashes. - i met with the budget holders and informed the project management office that they were happy to forecast this for future project, this action would have informed if there was not possible to re-phase the railings.
41
Why didn’t you just delay the event-facing works?
- My role was to ensure readiness for those events rather than adjust them. Therefore, I focused on identifying a deliverable solution within the existing timeframe rather than proposing changes to the client’s core objective. - Delaying the works was not appropriate because the events were fixed, high-profile commitments with reputational implications for the client.
42
How do you know this was the best option?
- Acceleration measures were either ineffective or disproportionate, whereas expanding the Intruder Detection System provided a feasible, cost-efficient solution that met the security requirement within the required timeframe. - i assessed these options against programme, cost, risk, and deliverability. - It aligned with the client’s objectives and avoided introducing further risk, which is why I advised it as the preferred option.
43
what was your role in terms of programming if you weren't writing the programmes yourself?
my role was to move beyond trying to recover a single project and instead advise the client on achieving their overall objective across all projects I advised on a more deliverable programme strategy given the constraints of plannign and the event dates.
44
What information might you include on the master programme compared to an individual project programme?
45
You mentioned that the railing upgrades programme was now forecast beyond the inaugural event after the LA’s cyber attack delayed planning permissions. How did you assess the impact of this delay on the project, and come to understand the completion of the railings project was now a problem?
- through regular catch-ups and monitoring of the programme and the milestones alongside the contractor teams, I noted that the actual date to receive the planning consent was delayed. - this was a key requirement to initiate activities, and by updating the programme with the new forecast date I could visualised and assess the impact - I could see all linked dependencies and activities that would also be delayed, with the final activity and completion now forecast to be delayed. - This delay went beyond the intended project completion but also conflicted with the inaugural high profile events.
46
Was there no float that could be used to recover the delay?
because of the planning delay, there was no longer any float to be used, no float in the critical path activity.
47
You mention that in lieu of adequate float, you investigated options to accelerate the railing works. What contract are you using, and how does this deal with acceleration?
- NEC4 - acceleration is a formal mechanism to bring fprward the completion date under clause 36.
48
How long does a contractor have to prepare their acceleration quote? How long does the PM have to accept this?
- the contractor has 3 weeks to provide a quote for acceleration - the project manager has 3 weeks to accept or reject, but they cannot make their own assessment only negotiate
49
Does the contractor have to agree to acceleration?
No the contractor is not obliged to agree unless a Z clause states otherwise
50
How did you establish the costs for hiring additional labour?
- requested quote from contractor for more labour - collaborated with internal cost manager to review the costs against market benchmarking and short schedule of rates - during this I dentified that the extra cost and lead time for security vetting would make this option not value for money.
51
How did you establish what programme betterment could be achieved in this option to determine that the costs outweighed the benefit?
- I compared the total cost and time saved versus the actual programme recovery gain it would provide - The vetting requirements constraint meant that high cost of more labour still carried risk of non delayed benefit if the vetting was delayed or unsuccessful - addtionally the noisy works constraint meant there was limited extra time any labour could work for. - there was also a resouce density constraint - there is only so many workers that can be on site upgrading the railings - therefore the extent that these recovery options shortened the programme was limited and contained risk without fully recovering the programme (completion still delayed)
52
Why was the extra hours option not viable? Could you not have applied for an out of hours approval?
- the local authority governing the area where the project was located had a no noisy works after 6pm weekdays and after 1pm on saturday, which limited the amount of extra hours that could be achieved. - fines up to £5000 for breach - the local Neighbourhood plan enforced an 'oasis of calm' policy and permissions for out of hours are typically given for major utility works or hours that cause road closures or legitimate public safety. Our requirement to simply complete works quicker would rarely be accepted.