What are your ‘Programming and Planning’ Level 2 examples?
Kingsmeadow office refurbishment:
Refining the contractor’s schedule to support floor-by-floor decant strategy.
Modular workplaces project:
Reviewing the contractor’s proposed programme and identifing unrealistic assumptions.
Birmingham:
checking the two project programme for conflict and finding duplicated supplier mobilisation
2a: What were the key constraints influencing the programme?
What was the key programming challenge on this project?
2a: How did business continuity affect sequencing decisions?
Why was business continuity a critical constraint?
2a: How did you develop the floor-by-floor decant strategy?
or How did you develop the decant sequence?
By consulting stakeholders and representatives to understand their minimum needs, and then sequencing works to maintain at least 180 desks at all times.
2a: Why did you prioritise ground-floor M&E and security works?
2a: Why was maintaining 180 desks critical?
What would have happened if this requirement was not met?
if this was not met;
- Reduced productivity due to impact on service provision
- stakeholder dissatisfaction, and
-potential project delay
2a: How did you manage the staggered completion and handover
of areas contractually?
2a: what happens at sectional completion
2a: Why did you only relocate teams once new areas were complete?
2a: How did stakeholder consultation influence the programme?
It ensured the sequencing aligned with operational needs and was practical to implement, rather than theorecially what would be the most efficient.
-it meant more phases but ensured business continuity
2a: What information did you use to inform your sequencing?
2a: How did you ensure logical sequencing of activities?
for example, furniture install before the IT install, before the internet cloud service connection before moving teams.
2a: How did you ensure the decant strategy was realistic?
2a: How did you determine the order of floor works?
Based on dependencies between the proposed layout and
-the availability of 180 desks and suitable relocation space.
2a: Why did you undertake site visits?
2a: What risks would arise if the decant strategy failed?
or What risks would arise if decanting was not properly planned?
Failure of the decant strategy would disrupt operations, delay the programme, increase cost through re-sequencing, and introduce safety and stakeholder risks.
2a: How did you manage dependencies between floors?
I ensured works were complete before safe relocations, allowed enough time between the contractor’s completion and the client’s IT and furniture supplier team to finalise the floors. I coordinated closely with stakeholders to avoid operational clashes, and I used the 2nd and 1st floor as float.
2a: What risks did your approach reduce?
2a: How did you communicate the decant plan to stakeholders?
2a: How would you monitor whether the decant was working in practice?
2a: What would you have done if capacity could not be maintained?
I would have escalated to the client and explored alternative solutions such as temporary accommodation.
2a: Were there any risks with a staggered approach to completion and taking
occupation of certain areas whilst refurbishment works continued in others?
what measures did you have in place?
yes;
2a: given all the risks of the sectional approach, what was the key driver?
2b: How did you review the contractor’s proposed programme?
or How did you assess the programme’s feasibility?