Managing Projects - Level 2 Flashcards

(17 cards)

1
Q

How did you monitor project progress? (DEFRA PM)

A

Through project trackers and regular reporting cycles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What tools did you use to track performance?

A

Microsoft project and Excel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you identify the cause of repeated late deliverables?

A

By reviewing the programme after the consultants said they were delayed due to their approvals process and identifying that internal quality assurance time was not included in the programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why was the lack of internal quality review time a problem?

A

Because it created unrealistic issue dates and reduced confidence in the programme, leading to knock-on delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What action did you take to address this?

A

I requested consultants build internal reviews into their programmes and align issue dates with formal client submission.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did adjusting issue dates improve programme reliability?

A

It aligned reported dates with realistic deliverables, reduced false optimism, and allowed dependencies to be managed more accurately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What would you have done if performance did not improve?

A

I would have escalated formally, reviewed resource allocation, and considered contractual remedies if necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you balance challenges with maintaining relationships?

A

By focusing on evidence, being clear about impacts, and framing challenge around project outcomes rather than individual performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is effective document control critical in managing projects? (Reading Accommodation Project)

A

Because decisions, procurement, and pricing rely on accurate and consistent information. Also client’s data may be at risk if care is not taken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What risks arise if tender information is inconsistent?

A

It undermined tender fairness and could have led to pricing inconsistencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you identify the SharePoint issue?

A

Through a document review following RIBA 4 sign-off, where I noticed file dates and versions had changed post-approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why was this a risk to a fair and accurate tender?

A

Because tenderers may price using different issued information, creating inconsistency and potential procurement non-compliance and risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What steps did you take to resolve the issue?

A

I raised the issue, requested re-issue of documents, and required an updated document register to reflect the correct information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did re-issuing the document register protect the client?

A

It ensured transparency, auditability, and a fair tender process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who is responsible for document control on a project?

A

Ultimately the client, delegated to the project manager, with clear responsibilities assigned to the design team.

17
Q

How would you prevent this from happening again?

A

By locking documents post-sign-off, enforcing version control, and requiring formal approval for any re-issue.