What is critical path analysis
A project analysis and planning method that allows a project to be completed in the shortest possible time
It starts by having a list of tasks and annotated with prerequisites
This is essentially just what needs to be done before the next task
What is a network diagram
It is a way of laying out tasks in the order they need to be completed and stating the times that each task should start and finish
What does a node contain
A node number
Earliest start time
Latest finish time
What is float time
Any period of time that a task can be delayed without any delays to the final project completion
What path is picked as the critical path
The one where the tasks cannot have any delays to them unless there will be a delay to the overall project finish time
What are the advantages of a critical path
Helps a business identify the fastest time to complete a project which should save the business time and money
If the project is related to a new product being released the business may get the product to market faster and benefit from first mover advantage
Businesses can plan their resources by ordering materials just when they need them or planning staff allocation
What are the drawbacks of critical path
Timings of activities are all based on estimates so the CPA network may not be fully accurate and delays can still occur
Projects can still be held up if suppliers miss their deadlines so it is still not fully in managers control
Managers may not have experience to plan their network well
The focus of cpa is about completing projects in time rather than the quality of the project