What remedial techniques did you advise for the cut edge corrosion at Coventry
Brush wire clean the affected area
Edgcoat giromax protection
Replacement is the more than half od the sheet has been damaged
What did you advise at Grimsby regarding the woodworm
I advised to determine the extent of infestation, whether it was live or dead. (no frass showing and darker holes - only corridor section was removed)
What further investigation did you advise at Hawthorn Street?
Boreholes to be undertaken to determine the foundation composition and condition (10m deep at 1m intervals). Drainage survey as a back up
Subsidence was detected (clay soils with reduced mositure) Either clay shrinkage by vegetation or leaking drains
Type of cracks that was evident - steeped cracking above the window wider at the top) and movement of the conrcete flags
What was required for substantiation of the off site materials payment request
Proof of payment (vesting certificate)
Insurance in place for the good and labelled in clients name
What alternative means of power were sought at Wellfield Close?
Diesel Generator
Solar/Hybrid generator
Battery powered
How did you identify non completion at Flyod Avenue and how did you advise your client on this?
On site review against contract document. I identified that several items had not been carried out.
I advised the client that PC could not be certified and to notify the contractor of the oitsanding works.
As there was no EOT request from the contractor i was able to produce a non completion certificate whichte and advised my client that they were entitled to levy liquidated damages
Also, for retention to still be withheld until the works reach PC
Things to consider when changing the roof covering in relation to Chesterfield Road
Market street - What is the minimum EPC for commercial and what is an EPC rating?
E - looking to change to a C in 2026
Energy Performance Certificate - document which displays how energy efficient a building is A-G
What did you advise the client at Wensley Road in relation to the two different solar panel types?
PV panels use sunlight to convert into electricty - simple to install and less maintenance
Solar smart - Use solar panels to heat water which is stored in a generator. More efficiency where this system can be monitored
Long terms value / Costs
At Cotmenhay how did you know a thermal cloak system would reduce thermal bridging
Steel column is exposed to thermal bridging due to being a good thermal conductor.
By wrapping the column with insulation this would reduce the heat flow
Part L of the Building Regs show that insulating structural elements as a means of reducing thermal bridging
What flood resilient measures did you advise the client at 24 Hawthorn?
Possible cause of the loose slates at Whaley Bridge
Talk me through the methodology at Whaley Bridge TDD
What was some of the defects that you advised the client on at Watery Lane?
-Water damaged suspended ceiling tiles
- blocked plygene gutters
- impact damage to profiled sheeting
- Rising damage to external brickwork
What was included in your terminal schedule of dilapidations report
Why did you go under hand as opposed to as a deed and vice versa
As a deed: long term risk projects, high value projects, used for collateral warranties
What is the methodology for carrying out the TSOD
what did you advise the client on in relation to the potential implications if the AO does not respond to the notice
If the AO does not respond under PWA 1996 within 14 days then a dispute has arisen.
The AO has a further 10 days to appoint a party wall surveyor
The works cannot proceed until a party wall award is drawn up
Can you go into more detail into the works at Castleford and how was this done safely
Wall was taken down using a sacffold and temporary febncing around to prveent access.
H&S documents and PD was involved.
The land was batted back to prevent land slip when the wall was removed. New foundations we inserted for rebilding the wall
Purpose of the party wall award and what does it include
Legally binding document
Protects both owners in that the works are lawful
details what works must be carried out and how this will be done
Includes:
-Parties
- Recitals: details of notice
- Works
- Arrangements/access
- Schedule of condition
Main sections under the PWA
3 - Notice requirements
5 - Dispute
7 - COMPENSATION
10 - Appointment of surveyors and award
What rights do parties have under hand as opposed to as a deed
As a deed: stronger security for third parties
How is a contract executed as a deed vs under hand?
Under hand: signature of the individual but no witness required
As a deed: must be signed by either two authorise signatories or one director in the presence of a witness
On your case study, how was the SE drawings included at tender?
The drawings were issued as part of the full tender documentation - became part of the contract docs