MIS573-Chapter3 Flashcards

(54 cards)

1
Q

A _____ is usually not necessary to the Scrum method, because Scrum implies that team members work as a self-directed group.

A

team charter (Because Scrum implies that team members work as a self-directed group, coached by the ScrumMaster, a team charter should not be necessary.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A milestone list is an output associated with the Project Scope Management knowledge area.

A

False (A milestone list is an output associated with the Project Schedule Management knowledge area.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.

A

True (A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in which processes?

A

closing (Closing processes include formalizing acceptance of the project or project phase and ending it efficiently. Administrative activities such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project are often involved in this process group.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Agile methods are used when deliverables have a low degree of change.

A

False (Agile is an adaptive product life cycle used when deliverables have a high degree of change and a high frequency of delivery.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An organization’s project management plan expresses the vision, mission, goals, objectives, and strategies of the organization.

A

False (The organization’s strategic plan expresses the vision, mission, goals, objectives, and strategies of the organization.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An organizational process assets update is the output of which closing process?

A

project integration management (The closing process involves gaining stakeholder and customer acceptance of the final products and services and then bringing the project or project phase to an orderly end. It includes verifying that all of the deliverables are complete, and it often includes a final project report and presentation.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Decisions and actions taken in one knowledge area at a certain time rarely affect other knowledge areas.

A

False (roject management is an integrative endeavor; decisions and actions taken in one knowledge area at a certain time usually affect other knowledge areas.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Identifying the project sponsor is a pre-initiation task.

A

True (It is a good practice to lay the groundwork for a project before it officially starts. Senior managers often perform several tasks, sometimes called pre-initiation tasks. These include identifying the project sponsor and selecting the project manager.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In the Scrum method, during which meeting is the improvement of the product and process discussed?

A

sprint retrospective (The improvement of the product and process in the Scrum method is discussed at the sprint reflection meeting.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In the Scrum method, team members work as a self-directed group coached by the ScrumMaster.

A

True (Because Scrum implies that team members work as a self-directed group, coached by the ScrumMaster, a team contract should not be necessary.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Initiating and closing tasks are usually the longest and require the most amount of resources and time.

A

False (Initiating and closing tasks are usually the shortest (at the beginning and end of a project or phase, respectively), and they require the least resources and time.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Initiating processes are not required to end a project.

A

False (Initiating processes are also required to end a project. Someone must initiate activities to ensure that the project team completes all the work, documents lessons learned, assigns project resources, and that the customer accepts the work.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Initiating processes take place during each phase of a project.

A

True (Initiating processes include defining and authorizing a project or project phase. Initiating processes take place during each phase of a project.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Key outcomes of the executing process group are formal acceptance of the work and creation of closing documents.

A

False (Key outcomes of the closing process group are formal acceptance of the work and creation of closing documents, such as a final project report and lessons-learned report.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Kick-off meeting agendas are usually recorded in a Word document.

A

True (Kick-off meeting agendas are normally recorded in the form of Word documents.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Project initiation involves taking the actions necessary to ensure that activities in the project plan are completed.

A

False (Executing the project involves taking the actions necessary to ensure that activities in the project plan are completed. It also includes work required to introduce any new hardware, software, and procedures into normal operations.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value.

A

False (A burndown chart shows the cumulative work remaining in a sprint on a day by- day basis.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The DMAIC (Define, Measure, Analyze, Improve, and Control) methodology of the Six Sigma projects, is used to improve an existing business process.

A

True (Two main methodologies are used on Six Sigma projects: DMAIC (Define, Measure, Analyze, Improve, and Control) is used to improve an existing business process, and DMADV (Define, Measure, Analyze, Design, and Verify) is used to create new product or process designs to achieve predictable, defect-free performance.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The executing process group generally requires the most resources.

A

True (The executing process group takes the actions necessary to complete the work described in the planning activities. It should overlap the other process groups, and generally requires the most resources.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The level of activity and length of each process group varies for every project.

A

True (The level of activity and length of each process group varies for every project. Normally, executing tasks requires the most resources and time, followed by planning tasks.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The organization recognizes that a new project exists and completes a project charter during which processes for a new project?

A

initiating (While initiating processes for a new project, the organization recognizes that a new project exists, and completes a project charter as part of this recognition.)

23
Q

The output of the stakeholder management strategy results is a project charter.

A

False (The output of the stakeholder management strategy results is a stakeholder register.)

24
Q

The pre-initiation phase of a project using the Scrum method does not involve project charters, stakeholder management strategy, and kick-off meetings.

A

False (A project charter, stakeholder register, stakeholder management strategy, and kick-off meeting would be created as part of initiation in a project using the Scrum method.)

25
The project management plan is the output of which project planning process?
integration management (The project management plan,which is part of the planning process, is the output of project integration management.)
26
The project schedule management knowledge area maps to which process group through the activity of schedule control?
monitoring and controlling (The project time management knowledge area maps to the monitoring and controlling process group through the activity of schedule control.)
27
The project scope management knowledge area maps to which process group through the activities of scope validation and scope control?
monitoring and controlling (The project scope management knowledge area maps to the monitoring and controlling process group through the activities of scope validation and scope control.)
28
The project stakeholder management knowledge area maps to which process group by identifying stakeholders?
initiating (The project stakeholder management knowledge area maps to the initiating process group by identifying stakeholders.)
29
The Rational Unified Process (RUP) framework is incompatible with the PMBOK process.
False (According to RUP expert Bill Cottrell, “RUP embodies industry-standard management and technical methods and techniques to provide a software engineering process particularly suited to creating and maintaining component-based software system solutions.” Cottrell explained that you can tailor RUP to include the PMBOK process groups because several customers asked for that capability.)
30
The two main items for monitoring and controlling in the Scrum framework are the daily Scrum and the sprint retrospectives.
True (The two main items for monitoring and controlling in the Scrum framework are the daily Scrum and the sprint review.)
31
The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
True (The WBS is a very important tool in project management because it provides the basis for deciding how to do the work. The WBS also provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.)
32
What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process?
burndown chart (A burndown chart is an important artifact used to graphically display progress on each sprint.)
33
What is developed in the Project Integration Management knowledge area?
a project management plan (Developing a project management plan is a planning process falling under the Project Integration Management knowledge area.)
34
What is often the most difficult and unappreciated process in project management?
planning (Because planning is not always used to facilitate action, many people view it negatively. However, the main purpose of planning is to guide project execution. As such, plans must be realistic and useful, so a fair amount of time and effort must go into the process.)
35
What is one of the main outputs of the initiation process?
developing the project charter (The main outputs of the initiation process are a project charter and a stakeholder register.)
36
What is the main purpose of project plans?
guide project execution (Developing a project management plan is a planning process falling under the Project Integration Management knowledge area.)
37
What process provides enterprise environmental factors as an output?
project human resource management (Enterprise environmental factors are an output of the executing process of project human resource management.)
38
What processes include defining and authorizing a project or project phase?
Initiating (Initiating processes include defining and authorizing a project or project phase. Initiating processes take place during each phase of a project.)
39
What processes include devising and maintaining a workable scheme to ensure that the project addresses the organization’s needs?
Planning (Planning processes include devising and maintaining a workable scheme to ensure that the project addresses the organization’s needs. Projects include several plans, such as the scope management plan, schedule management plan, cost management plan, and procurement management plan.)
40
What tool provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance?
work breakdown structure (The WBS is a very important tool in project management because it provides the basis for deciding how to do the work. The WBS also provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.)
41
Which activity is a part of the Scrum planning process?
Creating sprint backlog (Creating product backlogs, sprint backlogs and release backlogs are all part of the planning process of the scrum.)
42
Which are outputs of the executing process of project integration management?
Deliverables (Deliverables are an output of the executing process of project integration management.)
43
Which framework is an iterative software development process that focuses on team productivity and delivers software best practices to all team members?
Rational Unified Process
44
Which is an example of a pre-initiation task?
Developing a business case for a project (It is good practice to lay the groundwork for a project before it officially starts. Senior managers often perform several tasks, sometimes called pre-initiation tasks which include the development of a business case for a project.)
45
Which is true about the agile method?
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product. (An agile approach is often used for projects in which the business team cannot clearly express the scope early in the product life cycle, but the team does want to provide a potentially shippable product earlier rather than later. An agile project team typically uses several iterations or deliveries of software instead of waiting until the end of the project to provide one product.)
46
Which planning process is associated with project scope management?
Collecting requirements (Process improvement plans are an output of project quality management.)
47
Which planning process is within the Project Scope Management knowledge area?
Creation of a WBS (Creation of a WBS is a planning process falling under the Project Scope Management knowledge area.)
48
Which process includes measuring progress toward project objectives and taking corrective action to match progress with the plan?
Monitoring and controlling (Monitoring and controlling is done throughout the life of a project and involves 9 of the 10 project management areas.)
49
Which process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end?
closing (The closing process involves gaining stakeholder and customer acceptance of the final products and services and then bringing the project or project phase to an orderly end. It includes verifying that all of the deliverables are complete, and it often includes a final project report and presentation.)
50
Which processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements?
executing (Executing processes include coordinating people and other resources to carry out the various plans and create the products, services, or results of the project or phase. Examples of executing processes include directing and managing project work, managing project knowledge, acquiring resources, and conducting procurements.)
51
Which project would be compatible with the use of the agile approach?
Projects that have more flexible scheduling (Projects with heavy constraints, inexperienced and dispersed teams, large risks, generally clear up-front requirements, and a fairly rigid completion date are best done using a predictive approach. In contrast, projects with less rigid constraints, experienced and preferably co-located teams, smaller risks, unclear requirements, and more flexible scheduling would be more compatible with an agile approach.)
52
The project cost management knowledge area maps to which process group through the activities of estimating costs and budget determination?
planning (The project cost management knowledge area maps to the planning process group through the activities of estimating costs and budget determination.)
53
Monitoring and controlling processes overlap all of the other project management process groups.
True (Monitoring and controlling processes overlap all of the other project management process groups because changes can occur at any time.)
54
The kick-off meeting is always held before the business case and project charter are completed.
False (A kick-off meeting is a meeting held at the beginning of a project so that stakeholders can meet each other, review the goals of the project, and discuss future plans. The kick-off meeting is often held after the business case and project charter are completed, but it could be held sooner, as needed.)