MIS573-Chapter7 Flashcards

(63 cards)

1
Q

A budgetary estimate is the most accurate of the three types of estimates.

A

False (A definitive estimate provides an accurate estimate of project costs. It provides details for purchases and estimates actual costs.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A negative schedule variance means that it took less time than planned to perform the work.

A

False (A negative schedule variance means that it took longer than planned to perform the work, and a positive schedule variance means that the work took less time than planned to perform.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A schedule performance index of one means that the project is on schedule.

A

True (The schedule performance index (SPI) is the ratio of earned value to planned value; it can be used to estimate the projected time to complete the project. A schedule performance index of one means the project is on schedule.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Analogous estimates are called activity-based costing.

A

False (Analogous estimates are also called top-down estimates. Such estimates use the actual cost of a previous, similar project as the basis for estimating the cost of the current project.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Analogous estimates are the most accurate technique to estimate costs.

A

False (Analogous estimates requires a good deal of expert judgment and is generally less costly than other techniques. However, it is also less accurate.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Budgetary estimates are made even before a project is officially started.

A

True (Many organizations develop budgets at least two years into the future. Budgetary estimates are made one to two years prior to project completion.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contingency reserves are also known as unknown unknowns.

A

False (Contingency reserves allow for future situations that may be partially planned for. They are sometimes called known unknowns.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Definitive estimates are made one year or less prior to project completion.

A

True (Definitive estimates are made one year or less prior to project completion. They provide an accurate estimate of project costs.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Determining the budget involves allocating the project cost estimate to individual work items over time.

A

True (Determining the budget involves allocating the project cost estimate to individual material resources or work items over time. These material resources or work items are based on the activities in the work breakdown structure for the project.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimates should become more accurate as time progresses.

A

True (Estimates are usually done at various stages of a project and should become more accurate as time progresses.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Good Earth, a company manufacturing packaged food products, sets up its stores in Baltonia. However, a year later, the company closes the store down due to high operating costs. In such a scenario, the money spent in paying for the rent of the store in Baltonia would be an example of which costs?

A

sunk (Sunk cost is money that has been spent in the past. When deciding what projects to invest in or continue, one should not include sunk costs.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How are profits best defined?

A

revenues minus expenditures (Profits are revenues minus expenditures. To increase profits, a company can increase revenues, decrease expenses, or try to do both.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs.

A

True (Management reserves allow for future situations that are unpredictable. For example, if a project manager gets sick for two weeks or an important supplier goes out of business, management reserves could be set aside to cover the resulting costs.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If cost variance is a positive number, it means that performing the work costs more than planned.

A

False (Cost variance (CV) is the earned value minus the actual cost. If cost variance is a negative number, it means that performing the work costs more than planned. If cost variance is a positive number, performing the work costs less than planned.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If the cost performance index (CPI) is less than 100 percent, the project is under budget.

A

False (If the CPI is less than one or less than 100 percent, the project is over budget. On the other hand, if the CPI is greater than one or more than 100 percent, the project is under budget.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In a bottom-up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.

A

True (The size of the individual work items and the experience of the estimators drive the accuracy of the estimates. Using smaller work items increases the accuracy of the cost estimate because the people assigned to do the work develop the cost estimate instead of someone unfamiliar with the work.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned.

A

False (Viewing earned value information in chart form helps in visualizing how a project is performing. If the actual cost line is always on or above the earned value line, it indicates that costs are equal to or more than planned.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Intangible costs can be easily measured in monetary terms.

A

False (Intangible costs or benefits are difficult to measure in monetary terms. Conversely, tangible costs or benefits can easily be measured in dollars.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

It is important for project managers to focus on indirect costs because they can be easily controlled.

A

False (Direct costs can be directly related to creating the products and services of the project. Project managers should focus on direct costs because they can be controlled.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

It is important for project managers to understand that every cost estimate is unique.

A

True (Every cost estimate is unique, just as every project is unique.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

IT project managers must be able to present and discuss project information both in financial and technical terms.

A

True (Most members of a company’s executive board have a better understanding of financial terms than IT terms, and are more interested in finance. Therefore, IT project managers need to be able to present and discuss project information both in financial terms and technical terms.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation.

A

True (One of the reasons why project cost estimates are very inaccurate is because human beings are biased toward underestimation. It is thus important for project managers and top management to review estimates and ask important questions to make sure the estimates are not biased.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Overrun is the additional percentage amount by which estimates exceed actual costs.

A

False (Overrun is the additional percentage or dollar amount by which actual costs exceed estimates.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Project managers must conduct cash flow analysis to determine net present value.

A

True (Cash flow analysis is a method of determining the estimated annual costs and benefits for a project and the resulting annual cash flow. Project managers must conduct cash flow analysis to determine net present value.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Soles is a footwear company which has recently set up its store in Ambrosia. To manufacture its products, Soles incurs a range of different costs. Which would be an example of an indirect cost?
Electricity used to run its factories (Indirect costs are not directly related to the products or services of the project, but are indirectly related to performing the project. For example, indirect costs would include the cost of electricity, paper towels, and other necessities in a large building that houses 1,000 employees who work on many projects.)
26
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
True (Most organizations use software to assist in various activities related to project cost management. Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.)
27
The formulas for variances and indexes start with EV, the earned value.
True (The formulas for variances and indexes start with EV, the earned value. Variances are calculated by subtracting the actual cost or planned value from EV, and indexes are calculated by dividing EV by the actual cost or planned value.)
28
The main goal of which process is to produce a cost baseline for measuring project performance and project funding requirements?
cost budgeting (The main goal of the cost budgeting process is to produce a cost baseline for measuring project performance and to determine project funding requirements. Determining the budget involves allocating the project cost estimate to individual material resources or work items over time.)
29
The primary output of the planning cost management process is a change request.
False (The main output of the planning cost management process process is a cost management plan. Planning cost management involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling project cost.)
30
What is a rough order of magnitude estimate also referred to as?
ballpark (A rough order of magnitude (ROM) estimate provides an estimate of what a project will cost. A ROM estimate can also be referred to as a ballpark estimate, a guesstimate, a swag, or a broad gauge.)
31
What is the purpose of a cost performance index (CPI)?
estimate the projected cost of completing the project (The cost performance index (CPI) is the ratio of earned value to actual cost; it can be used to estimate the projected cost of completing the project.)
32
What term is used for analogous estimates?
top-down (Analogous estimates use the actual cost of a previous, similar project as the basis for estimating the cost of the current project. They are also called top-down estimates.)
33
What type of estimate is a cost estimation tool used to allocate money into an organization’s budget?
budgetary (budgetary estimate is used to allocate money into an organization’s budget. Budgetary estimates are made one to two years prior to project completion.)
34
What type of estimate is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs?
definitive (A definitive estimate provides an accurate estimate of project costs. Definitive estimates are used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.)
35
What type of management includes the processes required to ensure that a project team completes a project within an approved budget?
project cost management (Project cost management includes the processes required to ensure that a project team completes a project within an approved budget. Project managers must make sure their projects are well defined, have accurate time and cost estimates, and have a realistic budget that they were involved in approving.)
36
When deciding what projects to invest in or continue, one should include sunk costs.
False (Sunk cost is money that has been spent in the past. When deciding what projects to invest in or continue, one should not include sunk costs.)
37
Which costs are difficult to measure in monetary terms?
Intangible costs (Intangible costs or benefits are difficult to measure in monetary terms.)
38
Which is an input of the process of controlling costs?
work performance data (The project management plan, project funding requirements, work performance data, and organizational process assets are inputs for controlling costs.)
39
Which is an output of the process of controlling costs?
cost forecasts (Outputs of the process of controlling costs are work performance information, cost forecasts, change requests, project management plan updates, project documents updates, and organizational process asset updates.)
40
Which is true of earned value?
It is an estimate of the value of the physical work actually completed. (The earned value (EV) is an estimate of the value of the physical work actually completed. EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date.)
41
Which is true of the schedule performance index (SPI)?
It can be used to estimate the projected time to complete the project. (The schedule performance index (SPI) is the ratio of earned value to planned value; it can be used to estimate the projected time to complete the project.)
42
Which process involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance?
determining the budget (Determining the budget involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.)
43
Which process involves developing an approximation of the costs of resources needed to complete a project?
estimating costs (Estimating costs involves developing an approximation or estimate of the costs of the resources needed to complete a project. The main outputs of the cost estimating process are activity cost estimates, basis of estimates, and project documents updates.)
44
Which process results in a cost baseline as a main output?
cost budgeting (Determining the budget involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance. The main outputs of the cost budgeting process are a cost baseline, project funding requirements, and project documents updates.)
45
Which reserves allow for future situations that are unpredictable?
Management reserves (Management reserves allow for future situations that are unpredictable. They are sometimes called unknown unknowns.)
46
Which statement best defines cost variance?
earned value minus the actual cost (Cost variance (CV) is the earned value minus the actual cost. If cost variance is a negative number, it means that performing the work costs more than planned. If cost variance is a positive number, performing the work costs less than planned.)
47
Which statement best defines schedule variance?
earned value minus the planned value (Schedule variance (SV) is the earned value minus the planned value. A negative schedule variance means that it took longer than planned to perform the work, and a positive schedule variance means that the work took less time than planned to perform.)
48
Which statement is true of analogous estimates?
They are most reliable when previous projects are similar in fact with current projects. (Analogous estimates use the actual cost of a previous, similar project as the basis for estimating the cost of the current project. They are most reliable when the previous projects are similar in fact, not just in appearance.)
49
Which statement is true of contingency reserves?
They allow for future situations that can be partially planned for. (Contingency reserves allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline.)
50
Which statement is true regarding indirect costs?
not directly related to the products or services of a project. (Indirect costs are not directly related to the products or services of the project, but are indirectly related to performing the project.)
51
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
analogous estimates (Analogous estimates use the actual cost of a previous, similar project as the basis for estimating the cost of the current project. This technique requires a good deal of expert judgment and is generally less costly than other techniques, but it is also less accurate.)
52
Which type of estimating uses project characteristics in a mathematical model to estimate project costs?
parametric (Parametric estimating uses project characteristics (parameters) in a mathematical model to estimate project costs.)
53
Work performance information and cost forecasts are main outputs of which process?
cost control (Controlling costs involves controlling changes to the project budget. The main outputs of the cost control process are work performance information, cost forecasts, change requests, project management plan updates, project documents updates, and organizational process assets updates.)
54
Which statement is true of a order of magnitude estimate?
It provides an estimate of what a project will cost. (A rough order of magnitude (ROM) estimate provides an estimate of what a project will cost. This type of estimate is done very early in a project or even before a project is officially started.)
55
The project management plan and project funding requirements are inputs of the process of controlling costs.
True (The project management plan, project funding requirements, work performance data, and organizational process assets are inputs for controlling costs.)
56
Newtech Inc. hires John for the position of a software programmer to work on their new project. Salary paid to John by Newtech Inc. would be an example of which type of costs?
direct (Direct costs can be directly related to creating the products and services of a project. For instance, direct costs include the salaries of people working full time on a project.)
57
Which process helps develop an accurate projection of a project’s financial expenses and benefits?
life cycle costing (Life cycle costing helps develop an accurate projection of a project’s financial costs and benefits. It allows one to see a big-picture view of the cost of a project throughout its life cycle.)
58
What does the process of controlling costs primarily involve?
managing changes to the project budget (Controlling costs involves controlling changes to the project budget. The main outputs of the cost control process are work performance information, cost forecasts, change requests, project management plan updates, project documents updates, and organizational process assets updates.)
59
What is another term used for budget?
planned value (The planned value (PV), also called the budget, is the portion of the approved total cost estimate planned to be spent on an activity during a given period.)
60
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.
True (In addition to creating cost estimates for the entire project and activity cost estimates, it is also important to provide supporting details for the estimates and updates to project documents. The supporting details include the ground rules and assumptions used in creating the estimate, a description of the project used as a basis for the estimate, and details on the cost estimation tools and techniques used to create the estimate.)
61
Which type of estimate should be used if the cost estimate for a project is used a basis for contract awards and performance reporting?
definitive (If the cost estimate for a project is a basis for contract awards and performance reporting, it should be a definitive estimate and as accurate as possible.)
62
Which is most likely to be a reason for inaccuracies in information technology cost estimates?
People lack estimating experience. (The people who develop software cost estimates often do not have much experience with cost estimation, especially for large projects. They also do not have enough accurate, reliable project data on which to base estimates.)
63
Which method is used for determining the estimated annual costs and benefits for a project?
Cash flow analysis (Cash flow analysis is a method for determining the estimated annual costs and benefits for a project and the resulting annual cash flow. Project managers must conduct cash flow analysis to determine net present value.)