MIS573-Chapter6 Flashcards

(66 cards)

1
Q

A dependency pertains to the sequencing of project activities or tasks.

A

True (A dependency or relationship pertains to the sequencing of project activities or tasks. Determining these relationships or dependencies among activities has a significant impact on developing and managing a project schedule.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.

A

False (The main advantage of using Gantt charts is that they provide a standard format for displaying planned and actual project schedule information.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.

A

False (The precedence diagramming method offers a number of advantages over the AOA technique. One advantage is that using this method avoids the need to use dummy activities.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.

A

False (A project management software can be used to draw network diagrams, determine the critical path for a project, create Gantt charts, and report, view, and filter specific project time management information.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A merge occurs when one node precedes multiple nodes.

A

False (A merge occurs when two or more nodes precede a single node. On the other hand, bursts occur when two or more activities follow a single node.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.

A

True (A schedule management plan includes information on reporting formats. This information describes the format and frequency of schedule reports required for the project. In addition, it also includes information on process descriptions and describes how all of the schedule management processes will be performed.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.

A

True (A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates. It allows the project manager to monitor schedule progress on individual tasks and the whole project.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?

A

estimate the duration of activities. (After working with key stakeholders to define activities, determine their dependencies, and estimate their resources, the next process in project schedule management is to estimate the duration of activities.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

An activity is an element of work that has an expected duration, cost, and resource requirements.

A

True (An activity or task is an element of work normally found on the work breakdown structure (WBS) that has expected duration, cost, and resource requirements.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Critical chain scheduling assumes that resources multitask and maximizes multitasking.

A

False (Critical chain scheduling is a method that considers limited resources when creating a project schedule and includes buffers to protect the project completion date. It assumes that resources do not multitask or at least minimize multitasking.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

During which relationship is the “from” activity unable to start until the “to” activity is started?

A

start-to-start (A start-to-start dependency is a relationship in which the “from” activity cannot start until the “to” activity or successor is started.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How does critical chain scheduling protect tasks on the critical chain from being delayed?

A

feeding buffers (Critical chain scheduling protects tasks on the critical chain from being delayed by using feeding buffers, which consist of time added before tasks on the critical chain if they are preceded by other tasks that are not on the critical path.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In a critical path analysis, the shortest path is what drives the completion date for the project.

A

False (In a critical path analysis, several tasks are done in parallel on projects, and most projects have multiple paths through a network diagram. The longest path or the path that contains the critical tasks is what drives the completion date for the project.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In a Gantt chart, thick black bars represent milestones achieved in a project.

A

False (Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in calendar form. In a Gantt chart, a black diamond symbol represents a milestone.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

A

False (The network diagram represents activities that must be done to complete the project. Not every item on the WBS needs to be shown on the network diagram; only activities with dependencies need to be shown.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In an AOA network diagram, what occurs when two or more activities follow a single node?

A

bursts (When creating an AOA network diagram, bursts occur when two or more activities follow a single node.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?

A

defining activities (The goal of defining activities is to ensure that the project team completely understands all the work it must do as part of the project scope so the team can start scheduling the work. Activity information is a required input to the other time management processes.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

In project schedule management, the ultimate goal of which process is to provide a basis for monitoring project progress for the time dimension of the project?

A

developing a schedule (The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the time dimension of the project. Project schedule management processes often go through several iterations before a project schedule is finalized.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

In project schedule management, what is the next step after defining project activities?

A

determining their dependencies (After defining project activities, the next step in project schedule management is sequencing them or determining their dependencies. The sequencing process involves evaluating the reasons for dependencies and the different types of dependencies.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

In project schedule management, which process generates the main outputs of an activity list, activity attributes, and a milestone list?

A

defining activities (In project schedule management, the main outputs of the sequencing activities process are an activity list, activity attributes, a milestone list, and project management plan updates.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

In project schedule management, which process involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?

A

developing the schedule (Developing the schedule involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule. Outputs include a schedule baseline, project schedule, schedule data, project calendars, project management plan updates, and project documents updates.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?

A

estimating activity durations (Estimating activity durations involves estimating the number of work periods that are needed to complete individual activities. Outputs include activity duration estimates and project documents updates.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

A

sequencing activities (Sequencing activities involves identifying and documenting the relationships between project activities. The main outputs of this process include project schedule network diagrams and project documents updates.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

In project schedule management, which process primarily involves checking and managing changes to the project schedule?

A

controlling the schedule (In project schedule management, the process of controlling the schedule involves controlling and managing changes to the project schedule. Outputs include work performance information, schedule forecasts, and change requests among others.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.
True (The activity list and activity attributes should be in agreement with the work breakdown structure. Information is added to the activity attributes as it becomes available; this information includes logical relationships and resource requirements that are determined in later processes.)
26
Knowing the amount of float allows project managers to know whether a project schedule is flexible.
True (Knowing the amount of float or slack allows project managers to know whether the schedule is flexible and how flexible it might be. A fast and easy way to determine early and late start and finish dates and free and total slack amounts for activities is by using project management software.)
27
Milestones are easy to achieve and are always achieved through one main activity.
False (A milestone on a project is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone, but the milestone itself is like a marker to help in identifying necessary activities.)
28
Network diagrams are the preferred technique for showing activity sequencing.
True (Network diagrams are the preferred technique for showing activity sequencing. A network diagram is a schematic display of the logical relationships among project activities and their sequencing.)
29
One of PERT’s main disadvantages is that it does not address the risk associated with duration estimates.
False (PERT’s main disadvantages are that it involves more work than CPM because it requires several duration estimates, and there are better probabilistic methods for assessing schedule risk.)
30
Project schedules grow out of basic documents such as the project charter.
True (Project schedules grow out of the basic documents that initiate a project. The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule.)
31
Start-to-finish relationships are the most frequently used dependencies between activities.
False (One of the four types of dependencies or relationships between activities is the start-to-finish dependency. This is a relationship in which the “from” activity must start before the “to” activity can be finished. This type of relationship is rarely used, but it is appropriate in some cases.)
32
The arrows in a network diagram represent missed milestones in a project.
False (A network diagram is a schematic display of the logical relationships among project activities and their sequencing. The arrows in a network diagram represent the activity sequencing or relationships between tasks.)
33
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
longest; shortest (A critical path for a project is the series of activities that determine the earliest time by which the project can be completed. It is the longest path through the network diagram and has the least amount of slack or float.)
34
The critical path on a project can change as the project progresses.
True (The critical path represents the shortest time required to complete a project. The critical path on a project can change as the project progresses.)
35
The final process in project schedule management is developing the schedule.
False (The final process in project time management is controlling the schedule, Like scope control, schedule control is a portion of the integrated change control process under project integration management.)
36
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
False (The main advantage of crashing is that it shortens the time needed to finish a project. The main disadvantage is that it often increases total project costs.)
37
The technique of fast tracking can result in lengthening the project schedule.
True (The main disadvantage of fast tracking is that it can lengthen the project schedule because starting some tasks too soon often increases project risk and results in rework.)
38
In project schedule management, the ultimate goal of which process is to provide a basis for monitoring progress for the time dimension of the project?
developing a schedule (The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the time dimension of the project. Project schedule management processes often go through several iterations before a project schedule is finalized.)
39
To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.
True (Defining activities involves identifying the specific actions that will produce the project deliverables in enough detail to determine resource and schedule estimates. The project team reviews the schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets to begin defining activities.)
40
What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?
PERT uses different duration estimates whereas CPM uses one specific duration estimate. (PERT uses probabilistic time estimates —duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations —instead of one specific or discrete duration estimate, as CPM does.)
41
What is the first process involved in project schedule management?
Planning schedule management (Planning schedule management is the first process in project schedule management and involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule.)
42
What is the latest possible time an activity might begin without delaying the project finish date?
late start date (The late start date is the latest possible time an activity might begin without delaying the project finish date.)
43
What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?
total slack (Total slack or total float is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.)
44
What term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities?
free slack (A technique that can help project managers make schedule trade-offs is determining the free slack and total slack for each project activity. Free slack or free float is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.)
45
Which dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options?
discretionary (Discretionary dependencies are defined by the project team. They are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.)
46
Which dependencies do AOA network diagrams use?
finish-to-start (A finish-to-start dependency is the most common type of relationship or dependency and AOA network diagrams use only finish-to-start dependencies. It is a relationship in which the “from” activity or predecessor must finish before the “to” activity or successor can start.)
47
Which dependencies involve relationships between project and non-project activities?
external (External dependencies involve relationships between project and non-project activities.)
48
Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?
project charter (The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule.)
49
Which is a similarity between scope control and schedule control?
Both are portions of the integrated change control process under project integration management. (Like scope control, schedule control is a portion of the integrated change control process under project integration management. Controlling the schedule is the final process in project time management.)
50
Which is a similarity between the crashing and fast tracking?
both can shorten the time needed to finish a project (The main advantage of fast tracking, like crashing, is that it can shorten the time needed to finish a project.)
51
Which is an output of schedule control?
change requests (The main outputs of schedule control include work performance measurements, organizational process assets updates such as lessons-learned reports related to schedule control, change requests, project management plan updates, and project documents updates.)
52
Which is one of the main outputs of estimating activity resources process?
project documents update (Project documents update is one of the main outputs of the Estimating Activity Resources process.)
53
Which is true of dummy activities?
They show logical relationships between activities. (Dummy activities have no duration and no resources, but are occasionally needed on AOA network diagrams to show logical relationships between activities.)
54
Which law states that work expands to fill the time allowed?
Parkinson's Law (Parkinson’s Law states that work expands to fill the time allowed.)
55
Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
defining activities (In project schedule management, the process of defining activities involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.)
56
Which provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format?
Gantt charts (Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in calendar form. They are sometimes referred to as bar charts because the activities’ start and end dates are shown as horizontal bars.)
57
Which statement best describes the difference between an activity list and an activity attribute?
An activity attribute provides more schedule-related information about each activity than an activity list. (The activity list is a tabulation of activities to be included on a project schedule. The list should include the activity name, an activity identifier or number, and a brief description of the activity. The activity attributes provide more schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, and so forth.)
58
Which technique involves doing activities in parallel that one would normally do in sequence?
Fast tracking (Fast tracking involves doing activities in parallel that one would normally do in sequence. The main advantage of fast tracking is that it can shorten the time needed to finish a project.)
59
Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?
crashing (Crashing is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost. The main advantage of crashing is shortening the time needed to finish a project.)
60
Which term is used for a significant event on a project that normally has no duration?
milestone (A milestone on a project is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone, but the milestone itself is like a marker to help in identifying necessary activities.)
61
Which type of dependencies are inherent in the nature of work being performed on a project?
mandatory (Mandatory dependencies are inherent in the nature of work being performed on a project. They are sometimes referred to as hard logic.)
62
Which is true of a finish-to-finish dependency?
It is a dependency in which the “from” activity must be finished before the “to” activity can be finished. (A finish-to-finish dependency is a relationship in which the “from” activity must be finished before the “to” activity can be finished. One task cannot finish before another finishes.)
63
Which network diagramming technique uses boxes to represent activities?
PDM (The precedence diagramming method (PDM) is a network diagramming technique in which boxes represent activities. It is particularly useful for visualizing certain types of time relationships.)
64
Which technique involves network diagramming and is used primarily to predict total project duration?
critical path analysis (Critical path method (CPM) —also called critical path analysis —is a network diagramming technique used to predict total project duration. This important tool helps combat project schedule overruns.)
65
Which statement is true of bottom-up estimates?
They are time-intensive and expensive to develop. (Bottom-up estimates involve estimating the costs of individual work items or activities and summing them to get a project total. The drawback with bottom-up estimates is that they are usually time-intensive and therefore expensive to develop.)
66
A backward pass through the network diagram determines the early start and early finish dates for each activity.
False (A backward pass through the network diagram determines the late start and late finish dates for each activity. In contrast, a forward pass determines the early start and early finish dates for each activity.)