What is Activity on Node ?
A type of network diagram used in project management
Shows tasks as boxes (nodes) connected by arrows.
Arrows show the order tasks must be done.
Helps plan sequence and project timeline.
Critical Path
The longest path from start to finish, determining the shortest possible time the project can finish.
If any task on this path is delayed → whole project is delayed
Components of Activity -On Node Diagram
→ Nodes - circles/ boxes
→ Arrows
→ Duration Estimates
→ Float / Slack
→ Early start Early finish
→ Late start Late finish
Expert Judgement Method
Ask experts for their experience-based guesses
They estimate how long tasks will take.
👉 Think: “When in doubt, ask the expert out.”
Parametric Method
Uses numbers + past data to estimate time.
Based on parameters (e.g., size, cost, quantity) that affect duration.
👉 Think: “Measure by the numbers.”