Level 1 - Case Study
What are the maximum NEC3 time-scales for Compensation events if the Contractor notifies the PM?
Level 1 - Case study
How does this sequence differ if the PM was to notify the Contractor?
Level 1 - Case Study
How long did the PM on your project have to respond to the contractor’s quotations and is this always the case?
Level 1 - Case Study
What would happen if the PM failed to respond to the Contractors Quotation worth £176K on your project?
Level 1 - Case Study
What are the advantages of NEC over JCT?
Level 1 - Case study
What are the key differences between NEC3 & 4?
NEC4 includes changes such as;
1. Terminology
- Employer > Client
- Works Information > Scope
- Gender neutral
- Risk register > Early warning register
- Employers risk > Clients liabilities
Level 1 - Case Study
Why was Option A used on your project?
Level 1 - Case study
What are the pitfalls of using Option A?
Level 1 - Case study
How is the risk of no part payment overcome?
Level 1 - Case study
Why did you not utilise Option C?
Level 2 - Case study
Why was the shorter schedule of cost components not used in agreeing the CE?
It was pre-agreed to use tender rates or pro-rata rates where applicable.
Level 1 - Case study
You say you would instruct the contractor to provide several sub-contract prices next time one element accounts for such a large portion of the project, why was this not done initially?
What clauses relate to damages and sectional completion?
Case Study
Why was a 2-stage tendering process chosen?
Case Study
Did you advise on other potential tender options?
Case Study
Competitive single-stage doesn’t give the buildabilty advice to the design
Case Study
What other tender strategies offer programme benefits and buildability advise?
Case Study
How do these alternate tender options differ from a 2-stage?
Case Study
You mentioned that you considered a traditional procurement route as this would likely obtain competitive tenders, why only likely whats a scenario whereby it wouldn’t obtain a more competitive tender comparatively to a 2-stage?
Case Study
What information did you ask the contractor for in their 1st stage tender?
You mention re-tendering the mechancal sub-contract to get more then one price back, how did this effect programme seen as this was the key driver?
What in-house data did you use?
Case Study
How is it possible for other cost data to be applied to this project?
How did you check the rates for the building elements within the tender?