Level 3 - Sectional completion
LED project - Tell me about when you provided reasoned advice on any specific matters of a contract and why?
Level 3 - Sectional completion
What were the benefits of dividing the contract into sections, as apposed to doing it any other way?
Level 3 - Contract selection
Why did you advise on a JCT IC 2016?
Why were other forms or suites discarded?
Level 3 - LDs
On your LED lighting project, how did you advise your Client on the Liquidated Damages provision in the contract?
Level 1 - LDs
What are the risks of unreasonable LD amounts?
Level 1 - LDs
What are the risks of under/over valuing or leaving LD’s blank?
Level 1 - LDs
What are the Pro’s and Con’s of Unliquidated Damages?
Pro’s
* Employer could be compensated for sums not previous considered or forseeable
Con’s
* Employer has to prove actual loss, remoteness and loss mitigation
* Hard to prove
* Contractor doesn’t know their liability and cannot budget for risk of delay or adjust tender accordingly.
Level 2 - LDs
On your LED project, what considerations were mad in calculating the LD’s?
Level 1 - LDs
What are the advantages of LD’s?
Level 3 - Completion
On your LED Lighting scheme, how did you advise your client before including Sectional Completion provisions in the contract?
Level 1 - Completion
What are the advantages of sectional completion?
Level 1 - Completion
What are the consequences of completion?
Level 1 - Design potions
What is CDP?
Level 1 - Design portions
What is required from the contractor for their CDP?
Level 1
Post completion, can the contractor still be liable for damages?
Level 2 - Contract practice
You mention preparing contract documents, can you tell me what you’d include within a contract document?
Depends on standard form or suite of contracts, but namely;
JCT –
* Contract particulars
* Contract drawings
* Contract bills/pricing schedule,
* CDP analysis,
* Contractors proposal,
* Employers requirements.
* Technical specification
NEC –
* Works information/Scope
* Contract data,
* Activity schedule/BoQ
* Programme
* Site information
Level 1 - Retention
When is retention released to the contractor?
Level 2 - Valuation
You mention carrying out interim valuations, what did you include/consider when valuing the contractors interim application?
Ascertaining sums to be included in gross valuations such as;
1. Preliminaries
2. Works executed
3. Design fees
4. Provisional sum adjustment
5. Approximate quantities adjustments
5. Prime cost sums adjustments
6. Dayworks
7. Materials on-site
8. Materials off-site
9. Loss & expense
10. Variations
Level 2 - Valuations
What considerations should be made when valuing materials on-site?
Level 2 - Valuations
What are the considerations when valuing materials off-site?
Level 2 - Contract selection
You mention the importance of influencing factors when selecting the appropriate contract, what considerations did you make before advising your client on appropriate contract selection?
Level 2 - Case study
In your case study you mentioned that you managed a 2-stage tender strategy, how did you secure the contractors services for design input for the 1st stage?
Level 1 - Contract Practice
What are the requirements of a contract?
Level 1 - Rentention
What is Retention?