Contract Administration Flashcards

(52 cards)

1
Q

What are the main parts of the JCT Contract ?

A

Recitals
Articles
Contract particulars
Attestation
Conditions
Schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When would you use JCT Minor works?

A

Project works have a value of up to £200,00
Works are of a simple nature and a short duration
Design to be completed prior to contract execution
Lump sum contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would you use JCT intermediate contract ?

A

Project duration is within one year
Straight forward construction
Design complete prior to execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

JCT standard contract with quantities ?

A

Design completed prior to contract execution
Contractor takes risk of rates
Employer takes risk of errors in the bill
Bill of quants is used
Lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When would you use standard building contract without quantities?

A

Design completed prior to execution
No bill of quants
Contractor owns risk for both rates and quants
Lump sum
Contract docs include drawings, specifications and schedule of rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you use standard building contract with approximate quantities ?

A

Re measurable contract
Design incomplete prior to contract execution
Approx BOQ is prepared
No fixed contract sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When would you use JCT D&B?

A

Contractors proposals form the basis of the contract
Contractor is responsible for design and construction
Role of EA is used instead of QS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do relevant events mean?

A

Contractor is granted an extension of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does an extension of time mean?

A

Employer cannot claim liquidated damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are liquidated damages?

A

A genuine pre-estimate of the financial loss incurred due to project programme delay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are some examples of relevant events?

A

There are 13 relevant events
Examples include: exceptionally adverse weather conditions, deferment of site possession, variations, instructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are relevant matters?

A

specific events or issues for which the employer is responsible that cause disruption to the regular progress of the works, entitling the contractor to claim direct loss and/or expense. For example, failure to provide access to the site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How much retention should be retained ?

A

Typically 3%-5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the contract limitation periods ?

A

6 years if executed as an underhand
12 years If executed as a deed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the advantages of using the JCT contract suite ?

A

Considered to be industry standard
Covers most forms of procurement and building types
Comprehensive in detail
Considered fair and reasonable and not bias to either party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the Disadvantages of JCT suite of contracts?

A

Long and complex.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is insurance option A in a JCT contract?

A

Option A: All risks insurance of the works by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is insurance Option B in a JCT contract?

A

Option B: all risks insurance of the works by the employers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is insurance option C in a JCT contract?

A

Option C: the employer is required to take out and maintain
(a) a joint names policy in respect of the existing structures and their contents, and
(b) a joint names policy for all risks insurance for the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

When are the different insurance options in jct used?

A

Options A and B are used on new build structures
Option C is used for refurbishment or remediation projects to an existing building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How does JCT define a joint names policy ?

A

Where the employer and contractor are both included as composite insureds, meaning the insurer cannot recover costs from either party after a payout. Protects both the employer and subcontractor by removing all abilities for the insurer to sue one part and recoup its losses, thereby preventing delays and disputes related to fault during the claim process.

22
Q

What is a joint names policy?

A

A policy that is in the names of two parties (the employer and contractor). Under this policy the insurance provider will have no right to subrogation, even if it is one of the insured parties that have caused the loss for which the insurance provider has to pay out.

23
Q

What is subrogation?

A

Is a concept that allows an insurance company that has paid a loss to step into the shoes of who it is insuring to then sue the party that has caused the loss

24
Q

What are the key differences between JCT and NEC

A
  • NEC is drafted in plain English and provides for simpler language so is easier to understand
  • NEC uses early warnings and compensation events
  • NEC uses 6 main options and various secondary clauses whereas JCT uses separate contracts
    -NEC the programme is a contract document
  • JCT allows for provisional sums and NEC does not
25
What is the difference between NEC3 and NEC4?
NEC4 has introduced 2 new contracts: - Design build and operate contract - combines design, construction, operation and/or maintenance to enable procurement from a single supplier - Alliance contract - clients who wish to enter into a single contract with several participants - contract language is gender neutral - contractor is to submit an application for payment rather than the PM being obliged to assess if they fail to submit the application
26
Can you give me an overview of the NEC4 contract?
It was developed by the institution of civil engineers and is known for its collaborative and flexible approach. It aims to promote cooperation, clarity and fair risk allocation for the parties involved. There are six main options to choose from (options A to F)
27
What is a LD holiday or LD free period?
This is essentially just a grace period during which the contractor has no commercial liability for delay.
28
What is the implication of leaving the damage clause blank?
If the Claude is left blank , then the employer can pursue the contractor for unliquidated damages if they choose to do so.
29
What is the difference between liquidated and unliquidated damages?
Contracting parties might agree to pay a certain amount on breach of the contract. When such provisions are created in the contract they are known as liquidated damages. Unliquidated damages are granted by the courts based on an assessment of the loss or injury caused to the party suffering such breach of contract.
30
What are the advantages of standard forms over bespoke contracts?
Written by legal experts. Rights and obligations of each party are clearly set out to the required level of detail. Parties should be familiar with the provisions
31
What are the disadvantages of bespoke contracts?
Familiarity are decreased as they are rarely used. Expensive to draft (legal fees). May be poorly drafted and lead to ambiguity. Clauses/provisions might be untested in court.
32
What are some risks associated with amending a standard contract?
Amendments can spoil the balance of risk allocation. Can create legal uncertainty. Amendments must be reasonable and comply with legislation . Courts can strike out amendments if contrary to good faith.
33
When would you use the JCT Intermediate Contract.
The contract is designed for construction projects involving all recognised trades and skills of the industry. Intermediate building contracts are suitable for ‘ Projects Procured via the Traditional Method’.
34
What are the 6 main options under the NEC4 ECC contract?
Option A: Priced contract with activity schedule. B: Priced contract with bill of quantities. C: Target contract with activity schedule. D: Target contract with bill of quantities. E: Cost-reimbursable contract. F: Management contract.
35
What is net contribution clause ?
This clause comes into effect when a loss is caused by more than one party, such as an architect and a contractor both contributing to a design defect. The party with the net contribution clause is only responsible for paying their specific share of the loss, as determined by the court.
36
What are general damages?
Compensation for actual, unquantified losses resulting from a breach in contract. They are used when liquidated damages are absent or the contractual remedies do not apply. Also known as unliquidated damages
37
What is the implication of inserting ‘nil’ or £0 against the damage clause?
This would mean that liquidated damages do not apply and could also prevent the employer from perusing the contractor for unliquidated damages.
38
What collateral warranty type did you use for the NDA project and which clause in the contract covers this?
This was a sub- contractor warranty and the information concerning this in the contract is clause 7.8
39
Why was it advised for a colateral warranty to be drawn between the client and the electrical sub contractor ?
Electrical systems are complex and require expert knowledge to design and implement correctly, this collateral warranty link provides a safety net for the client in regards to design liability, allowing the client to seek redress for defects.
40
What are the key changes from JCT 2016 to 2024
- more inclusive language - implementation in article 7 to identify duty holders under the Building Safety Act 2022 (principal designer and principal contractor) - epidemic clauses have been added in relation to relevant events and matters - integration of sustainability - clause 21.5 includes a provision for the contractor to make a suggestion where changes to the works will benefit the environment
41
What schedule deals with extensions or times and relevant events in JCT ?
Section 2
42
What schedule deals with relevant matters in JCT?
Section 4 Clause 4.12 for D&B Clause 4.5 for Standard building contract
43
What clause is the final statement/certificate and payment under in JCT standard, intermediate and D&B contracts?
D&B - 4.24 Intermediate - 4.21 Standard - 4.26
44
How is a contract administrator defined?
Person appointed by the employer to manage the contract, acting as their gent whilst also performing impartial duties to ensure the contract is followed correctly
45
What is n employers agent?
Acts as the clients representative on a D&B contract, administrating the contract and managing the project on their behalf
46
What are the consequences of a non completion certificate ?
- certificate of non completion issued by the CA - employer must write to the contractor to notify them of their intent to levy LADs - employer must issue a pay less notice to recover the LAD’s
47
What are the Certificates issued by a contract administrator?
- interim payment certificates - practical completion certificate - certification of making good defects ( all defects identified after PC have been fixed) - final certificate (end of defects liability, all accounts settled and final release of retention) - certificate of non completion - extension of time
48
What is included in contract documents?
- actual contract - working drawings - pricing document - specifications - schedule of contract amendments
49
How is the final statement and payment executed under JCT Standard Building Contract
Practical completion occurs and within 6 months the contractor must submit their adjusted contract sum (if they fail to do so a 1 month notice to supply is given) . After this has been received the QS has 3 months to prepare the statement showing the adjusted contract sum. At the end of the rectification period, the certificate or making good defects or copies of statement and ascertainment, the contract administrator has 2 months to issue the final certificate. The due date for payment is the final day of this 2 month period
50
How is the final statement and payment executed under JCT intermediate Building Contract
At practical completion, the contractor has 6 months to submit their adjusted contract sum (if they fail to do so a further 1 month notice is given). The QS then has 3 months to prepare the statement showing the adjusted contract sum. At the end of the rectification period, certificate of making good defects or issue of statement and ascertainment the contract administrator must issue the final statement within 28 days and the final date for payment is the last day do this 28 day period.
51
How is the final statement and payment executed under JCT Design and Build Contract
The final statement must be submitted to the employer within 3 months of practical completion. If they fail to do this, the employer notifies that unless they submit within 2 months from the date of the notice, the employer may issue the final statement. The final date for payment is 1 month after : - end of the rectification period - certificate of making good defects - date of submission of final payment
52
How is the final statement and payment executed under JCT Minor works Contract
after practical completion (as per period stated in the contract) the contractor must the provide the CA with documentation required for the final payment. The final date for payment is 28 days after this information is provided The final certificate is then issued 5 days after the final payment due date