What are the main parts of the JCT Contract ?
Recitals
Articles
Contract particulars
Attestation
Conditions
Schedules
When would you use JCT Minor works?
Project works have a value of up to £200,00
Works are of a simple nature and a short duration
Design to be completed prior to contract execution
Lump sum contract
When would you use JCT intermediate contract ?
Project duration is within one year
Straight forward construction
Design complete prior to execution
JCT standard contract with quantities ?
Design completed prior to contract execution
Contractor takes risk of rates
Employer takes risk of errors in the bill
Bill of quants is used
Lump sum
When would you use standard building contract without quantities?
Design completed prior to execution
No bill of quants
Contractor owns risk for both rates and quants
Lump sum
Contract docs include drawings, specifications and schedule of rates
When would you use standard building contract with approximate quantities ?
Re measurable contract
Design incomplete prior to contract execution
Approx BOQ is prepared
No fixed contract sum
When would you use JCT D&B?
Contractors proposals form the basis of the contract
Contractor is responsible for design and construction
Role of EA is used instead of QS
What do relevant events mean?
Contractor is granted an extension of time
What does an extension of time mean?
Employer cannot claim liquidated damages
What are liquidated damages?
A genuine pre-estimate of the financial loss incurred due to project programme delay
What are some examples of relevant events?
There are 13 relevant events
Examples include: exceptionally adverse weather conditions, deferment of site possession, variations, instructions
What are relevant matters?
specific events or issues for which the employer is responsible that cause disruption to the regular progress of the works, entitling the contractor to claim direct loss and/or expense. For example, failure to provide access to the site
How much retention should be retained ?
Typically 3%-5%
What are the contract limitation periods ?
6 years if executed as an underhand
12 years If executed as a deed
What are the advantages of using the JCT contract suite ?
Considered to be industry standard
Covers most forms of procurement and building types
Comprehensive in detail
Considered fair and reasonable and not bias to either party
What are the Disadvantages of JCT suite of contracts?
Long and complex.
What is insurance option A in a JCT contract?
Option A: All risks insurance of the works by the contractor
What is insurance Option B in a JCT contract?
Option B: all risks insurance of the works by the employers
What is insurance option C in a JCT contract?
Option C: the employer is required to take out and maintain
(a) a joint names policy in respect of the existing structures and their contents, and
(b) a joint names policy for all risks insurance for the works
When are the different insurance options in jct used?
Options A and B are used on new build structures
Option C is used for refurbishment or remediation projects to an existing building
How does JCT define a joint names policy ?
Where the employer and contractor are both included as composite insureds, meaning the insurer cannot recover costs from either party after a payout. Protects both the employer and subcontractor by removing all abilities for the insurer to sue one part and recoup its losses, thereby preventing delays and disputes related to fault during the claim process.
What is a joint names policy?
A policy that is in the names of two parties (the employer and contractor). Under this policy the insurance provider will have no right to subrogation, even if it is one of the insured parties that have caused the loss for which the insurance provider has to pay out.
What is subrogation?
Is a concept that allows an insurance company that has paid a loss to step into the shoes of who it is insuring to then sue the party that has caused the loss
What are the key differences between JCT and NEC