HVC Flashcards

(9 cards)

1
Q

Which of the following doors are control building pressure boundary doors?

A

control building chiller room doors, mechanical equip room EAST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

CBI actuates. How will equipment respond to CBI signal?

A

control room envelope outlet vent paths isolate, Train A control building filter starts. TSC inlet and outlet paths isolate, 30 mins later TSC inlet path opens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CB chiller has not been run for several weeks and is at ambient temp.

What is the max number of starts per hour allowed for this control building chiller?

A

two

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CB chiller has been run recently and is at normal op temp.

What is the max number of starts per hour allowed for this CB chiller?

A

one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a major concern with stopping all control building chiller room ventilation?

A

buildup of refrigerant gasses in room

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is there a fifteen min time delay for restarting a control building chiller after stopping it?

A

prevent damage to compressor and compressor motor by allowing at least fifteen min for the refrigerant cycle pressures to equalize (anti-recycle lockout)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is compressor C1C the preferred unit when restoring control building air bank pressure from 1600 to 2200 psig?

A

C1A and C1B cannot be continuously run more than 30 min at a time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the function of recirculation control valves?

A

maintain total system flow rate to ensure minimum flow through chilled water pumps and preclude challenges to chiller unit trips

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly