Resource Management Flashcards

(5 cards)

1
Q

What is resource smoothing?

A

Prioritising the deadline of the project by reallocating resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Resource levelling

A

Prioritising a project’s Resource constraint by utilising float and/or extending the project deadline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Critical chain?

A

The longest sequence of both project tasks and resource-dependent tasks that determines a project’s overall completion time

Considers: resource limitations and task dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a task dependency?

A

Relationships between tasks in a project that determine the order of their execution

Where one task cannot start or finish until another (a predecessor) has started or finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name the four key resource categories and the 2 sub-categories

A

Key:
1. Human (Labour)
2. Materials
3. Plant & equipment
4. Facilities

Sub-categories:
1. Consumable resources
2. Deployable resources

How well did you know this?