Resource Management Flashcards

(19 cards)

1
Q

Resource Management process

A

Planning: Plan resource management, estimate activity resources
Executing: Acquire resources, develop team, manage team
Monitoring & Controlling: Control resources (physical resources)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan Resource Management

A

Inputs: Project mgmt plan, project charter, project documents, EEFs, OPAs
Tools/Techniques: also WBS, text documents
Outputs: Resource management plan, team charter, updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Responsibility assignment matrix (RAM)

A

(Tool/Technique of Plan Resource Management)
Matrix of who has primary (P) or secondary (S) responsibility, by task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

RACI chart

A

(Tool/Technique of Plan Resource Management)
Responsible, Accountable, Consult, Inform - roles can be shared, except for Accountable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Organizational breakdown structure

A

(Tool/Technique of Plan Resource Management)
Shows which units/departments are involved in which work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Resource breakdown structure

A

(Tool/Technique of Plan Resource Management)
Grouped by types of resources, shows which units/departments are providing which specific resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Resource management plan

A

(Output of Plan Resource Management)
How resources (human and physical) will be added, managed, and released

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Team charter

A

(Output of Plan Resource Management)
Agreement on procedures for conflict resolution, meetings, work assignments, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Organizational theory

A

(Tool/Technique of Plan Resource Management)
Study of how maximize efficiency and productivity in an organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate Activity Resources

A

Inputs: resource mgmt plan, scope baseline, activity list, cost estimates
Tools/techniques: estimating (bottom-up, analogous, parametric, alternatives)
Outputs: resource breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Acquire Resources

A

i.e. acquire the final resources; e.g. hiring, procuring, negotiating
Inputs: resource mgmt plan, EEFs, OPAs
Outputs: staff and physical resources, resource calendar, project mgmt plan updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Resource histograms

A

(Tool/Technique of Estimate Activity Resources)
Shows resource requirements by week, e.g. % staff time required)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Pre-assignment

A

(Tool/Technique of Acquire Resources)
Resources assigned within the project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Negotiation

A

(Tool/Technique of Acquire Resources)
Both internal and external resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Virtual teams

A

(Tool/Technique of Acquire Resources)
Challenges and benefits based on distributed workforce

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Manage Team

A

Inputs: resource mgmt plan, issue log, lessons learned register, project team assignments, team charter
Tools/techniques: interpersonal and team skills
Outputs: change requests, issue log

17
Q

Issue log

A

(Input to Manage Team)
a.k.a issue register or action item logs
Tracks problems and resolutions

18
Q

Control Resources

A

relates to physical resources
Inputs: project documents (issue log, lessons learned, resource assignments, project schedule, resource requirements, RBS, risk register, agreements, work performance data
Tools/techniques: performance reviews, trend analysis, alternatives analysis, PMIS, problem-solving methods
Outputs: work performance information, project documents updates, project mgmt plan updates

19
Q

Problem-solving methods

A

(Tool/Technique of Control Resources)
1. Define root problem
2. Analyze the problem
3. Pick a solution
4. Implement chosen solution
5. Review and confirm solution has solved problem