Schedule Management Flashcards

(41 cards)

1
Q

Schedule management process

A

Plan schedule management
Define activities
Sequence activities
Estimate activity durations
Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule management plan

A

Formal or informal; part of project mgmt plan
Includes time scale being used, schedule baseline, allowable variances, schedule change control processes, reporting, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define Activities

A

Inputs: project mgmt plan, EEFs, OPAs
Outputs: Activity list and Activity attributes, milestone list, change requests; one of only a few processes that specifically result in change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Rolling wave planning

A

(Define Activities tool/technique)
Developing a high-level plan, then creating detailed plans as work develops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Decomposition

A

(Define Activities tool/technique)
WBS (deliverables) is part of Scope Management
Defining activities is part of Schedule Management
(Can happen at same time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity list

A

(Define Activities output)
List of all activities needed for project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity attributes

A

(Define Activities output)
Description/details of activities on the Activities List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Milestone list

A

(Define Activities output)
Significant events in project timeline
Are not work activities themselves, do not have a duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Sequence Activities

A

Inputs: Project documents
Outputs: Network diagram, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Precedence Diagramming Method (PDM)

A

Use of nodes/boxes to show activities, with arrows representing dependencies
Relationships:
Finish-to-Start (FS) - A must finish before B starts
Start-to-Start (SS) - A must start before B starts
Finish-to-Finish (FF) - A must finish before B finishes
Start-to-Finish (SF) - A must start before B finished (rare)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Dependencies determination

A

Mandatory (hard logic) - either inherent in work, or contractually required; identified by project team
Discretionary (soft logic) - based on preferences, can be modified as needed (e.g. schedule compression); identified by project team
External - e.g. government, supplier, etc.; identified by project manager
Internal - may be something project team can control; identified by project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Network diagram

A

Output of Sequence Events
Depicts activity flow in a logical order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Path convergence and divergence

A

Convergence - when 2/+ activities precede the subsequent activity
Divergence - when 2/+ activities follow an activity
Either/both cases indicated elevated risk for those activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Leads and lags

A

Lead - amount of time after activity A starts that activity B can start
Lag - amount of time after activity X finishes before activity Y can start or finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimate Activity Durations

A

Inputs: Activity list with activity attributes, assumption log, lessons learned register, resource breakdown structure, resource requirements
Outputs: Estimates, updates to project documents like activity attributes, assumption log lessons learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Analogous (top-down) estimating

A

(Tool/technique of Estimate Activity Durations)
Expert judgement + historical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Parametric estimating

A

(Tool/technique of Estimate Activity Durations)
Based on quantitative data
Regression analysis (scatter diagram) - looks for relationship between 2 variables
Learning curve - expected efficiency gains with repetition throughout project

18
Q

Three-point estimating

A

(Tool/technique of Estimate Activity Durations)
Optimistic (O), Pessimistic (P), and Most Likely (M) scenarios

19
Q

Beta distribution

A

(Tool/technique of Estimate Activity Durations)
Weighted average of three-point estimation scenarios, from program evaluation and review technique (PERT)
(P + 4M + O)/3

20
Q

Triangular distribution

A

(Tool/technique of Estimate Activity Durations)
Simple average of three-point estimation scenarios
(P + M + O)/3

21
Q

Bottom-up estimating

A

(Tool/technique of Estimate Activity Durations)
Detailed estimates for activity or work package, rolled up to a total amount

22
Q

Alternatives analysis

A

(Tool/technique of Estimate Activity Durations)
Considers buy-vs-build and similar alternatives
Used when estimates fall outside of project constraints

23
Q

Reserve analysis

A

(Tool/technique of Estimate Activity Durations)
Intersection of estimating and risk mgmt

24
Q

Padding vs. reserves

A

Reserves - calculated based on detailed estimates
Padding - arbitrary amount

25
Basis of estimates
(Output of Estimate Activity Durations) Explanation of how estimates formed, assumptions, constraints, and risks
26
Develop Schedule
Inputs: OPAs, project mgmt plan; define activities, sequence activities, and estimate durations outputs Outputs: project schedule, milestone and bar charts, schedule baseline, schedule data, change requests, project documents updates
27
Schedule model
Based on activities, duration estimates, dependencies, leads, and lags Used to produce the project schedule
28
Critical path method
(Tool/technique of Develop Schedule) Determines which path is the critical path Allows for calculating earliest and latest start, and earliest and latest finish for each activity
29
Forward and backward pass
In critical path method... Forward pass calculates earliest starts and finishes Backward pass calculates latest starts and finishes
30
Critical path
Path of activities with longest duration, and thus, 0 float
31
Near-critical path
Path with next longest duration The closer the critical and near-critical paths are in duration, the more risk is inherent in the project
32
Float (schedule flexibility)
Total float - amount of time an activity can be delayed without impacting the schedule (primary type of float) Free float - amount of time an activity can be delayed without impacting *early start* of successor Project float - amount of time a project can be delayed without impacting required completion date
33
Calculating float
Start formula: late start (LS) - early start (ES) Finish formula: late finish (LF) - early finish (EF) "There is a start formula and a finish formula, and we always begin late."
34
Schedule compression
Crashing - add or adjusting resources; results in increased costs (and possibly risk) Fast tracking - changes activities from serial to parallel; requires more attention to communication, and often results in rework, increased risk
35
Monte Carlo analysis
Computer simulation based on 3-point estimates Calculates probabilities of completing at a specific time or cost, and overall project risk
36
Resource optimization
Resource leveling - extends schedule but limits variation in # of resources needed at any given time Resource smoothing - a type of levelling, where activities are still completed within their float range
37
Milestone charts
(Output of Develop Schedule) Show key points along the project's duration Milestones have no duration
38
Bar charts
(Output of Develop Schedule) Show activity durations along projects duration Better at reporting and control than for planning
39
Schedule baseline
(Output of Develop Schedule) Version of the schedule model used to manage project, and evaluate performance against
40
Control Schedule
Tools/techniques: data analysis, PMIS Outputs: work performance information, schedule forecasts
41
Reestimating
Part of Control Schedule, ensures project stays on track to reach objectives