ECCS acceptance Criteria
HOTCC
HOTCC
SI block with pressure
When less than 2000psig
Low Pressure in PZR (1715psig)
Hi Steam Line D/P (100psig)
SI block with Tave
When 543 degrees
Hi Steam line flow
Hi-Hi CV pressure
Actions caused by SI
SPARE FCCC
Resetting auto SI signal
Resetting Manual SI
Must wait 2 minutes before pressing reset button. Unlike Auto signal the button cannot be pressed before 2 minutes.
Do components reposition after a SI signal is reset?
No, components do not reset
What signals must be reset individually?
Phase A
Phase B
HVH dampers
IVSW
CV ventilation isolation
Feedwater isolation
SI valves
which reposition
SI-867 A/B BIT inlets open
SI-870 A/B BIT outlets Open-Move
SI-841 A/B BIT Recirc to RWST Closed
SI-865 A/B/C Accumulator Oulets open
RHR-747 A/B RHR cold leg injection Open-Move
Interposing Relays are powered from?
IB-7A Train A
IB-3 Train B
Automatic Spray signal does what?
Manual Spray signal does what?
CV Ventilation Isolation does what?
Shuts:
CV Purge Valves
Pressure Relief Valves
Vacuum Relief Valves
Phase B valves
CC-716A-CC to RCP A/B/C and CRD Cool isolation
CC-716B-CC to RCP A/B/C and CRD Cool Isolation
cvc-381- RCP Seal Water Return * Important*
CC-735- CC from RCP A/B/C thermal barrier isolation
CC-730- CC from RCP A/B/C oil cool isolation
FCV-626- CC From RCP A/B/C thermal Barrier isolation
CCW to Containment basically
Steam Line isolation SI singals
Hi-Hi CV pressure (10psig)
High Steam Flow with Low stm line press or low tavg
Steam LIne Isolation is what?
Closure of MSIVs
Feedwater Isolations
Reactor Trip with Tavg <554 degrees does what to feedwater?
Shuts all FRVs
Hi-Hi S/G Level does what to feedwater?
SI actuation does what to Feedwater?
Must have 2 channels per E bus for UV and 3 channels per E bus for UF
Loss of 1 UV, restore within an hour
Loss of 2 UF, restore at least 1 within an hour
If above times cannot be met then declare EDG inop.