What are the two key phrases associated with adaptive scheduling?
The two key phrases are “incremental planning” and “iterations and releases.”
What is a roadmap in the context of adaptive scheduling?
A roadmap is a high-level list of items that outlines the direction and goals of the project.
What drives the roadmap in adaptive scheduling?
The vision of the project drives the roadmap. The roadmap drives the release plan
What do release plans establish in adaptive scheduling?
Release plans establish iterations, which are the chunks of work that are released to the customer.
How are features developed in adaptive scheduling?
Features can be developed in any order and are prioritized based on user stories.
What is a time box in adaptive scheduling?
A time box is a fixed period during which specific tasks or features are completed, often referred to as a sprint.
How does the team manage work in adaptive scheduling?
The team estimates and self-manages the work, deciding what tasks to take on rather than having tasks assigned to them.
What is the significance of user stories in adaptive scheduling?
User stories help prioritize features and tasks based on user needs and are sized in terms of hours for planning.
What is the term used to track how well the team is performing in adaptive scheduling?
The term is “velocity,” which measures the amount of work completed in a given time frame.
What happens to the backlog in adaptive scheduling?
The backlog is updated and reprioritized after each sprint based on the work completed and new items added.
When does the project owner consider the project done in adaptive scheduling?
The project owner considers the project done when the highest priority items are delivered.