Project structures Flashcards

(3 cards)

1
Q

How does Project manager’s authority and resource availability vary across the structures

A
  • Functional: Little or none (pm has to induce them to work)
  • Weak matrix: Limited
  • Balanced matrix: Low to moderate
  • Strong matrix: Moderate to high
  • Projectised: High to total
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Budget and technical control across the structures:

A
  • Functional: Functional manager
  • Weak matrix: Functional manager
  • Balanaced matrix: Mixed (PM responsible for schedule, cost and performance, FM is responsible for technical performance)
  • Strong matrix: Project manager
  • Projectised: Project manager
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PM’s role and administrative staff across the structures

A
  • Functional: Part time
  • Weak matrix: Part time
  • Balanaced matrix: Full time
  • Strong matrix: Full time
  • Projectised: Full time