Defining the network Flashcards

(4 cards)

1
Q

What is the main purpose of a network diagram?

A

The main purpose of a network diagram is to visualize the sequence of activities in a project, helping to understand the flow and dependencies between tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do we determine the order of activities in a network diagram?

A

The WBS gives a hierarchical list of all activities using which we determine the order by identifying which activities depend on the completion of others, establishing a sequence based on their relationships.

There is no sequence in WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an immediate predecessor in the context of network diagrams?

A

An immediate predecessor is an activity that must be completed directly before another activity can start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How many pieces of information does each activity box in a network diagram contain?

A

Each activity box contains nine pieces of information.
* Row 1: Earliest start, ID identification, Earliest finish
* Row 2: Float, description, float
* Row 3: Latest start, Duration, Latest finish

How well did you know this?