Purpose of RCP’s
- h/u RCS from cold plant conditions
Describe RCP’s
Labyrinth Seals function
Thermal Barrier /therm barr hx function
Radial bearing function
Describe flow rates/ pressures of seal injection
What disadvantages are there to loosing seal injection?
Describe #1 seal
Describe the low leakage shutdown seal (sds)
Describe #2 seal
Describe #3 seal
Describe CVCS-8141 A/B/C/D
- done when #1 fails => ensure all flow goes to #2 seal turning into film riding
Describe CVCS-8100/ 8112
CNMT isolation for seal return (phase A)
Describe RCP motor
RCP’s power supplies
1-1 (12kv) E
1-3 (12kv) E
1-2 (12kv) D
1-4 (12kv) D
RCP trips
B/U bkr - man local - oc - inst. oc Pri bkr - man switch - man local - 12 kv bus UV - 12 kv bus diff (current in = current out) - oc - RCP bus UF (A) - RCP bus UF (B)
Interlocks required to start RCP
- rack primary bkr to test
Or
- b/u bkr closed
- oil lift pump running > 120 sec
- oil lift pressure > 500 psig for 120 secWith RCP, running oil lift pump will s/d after 50 sec
How does CCW interface with RCP’s
Precautions and Limitations for RCP’s
Precautions and limitations for opening seal #1 bypass (CVCS-8142)
Why would you do this?
if your #1 seal is trashed and want to save lower radial bearing