NC Flashcards

(16 cards)

1
Q

What are the NC priority loads

A
  • RCP’s
  • CEDM normal ACU
  • Normal chillers
  • Nuc sample coolers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the NC non-priority loads

A

BEAN LAWGS

  • BAC
  • Evap
  • AS vent condenser
  • Non-nuc sample coolers
  • Letdown HX
  • AS Rad monitor
  • Waste gas compressors
  • SFP HX (can be supplied by EW)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the NC Rad monitor

A
  • RU-6 - Normal
  • If x-tied to EW RU-2 or 3 since Rad monitor is not in
    loop
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What will auto start the STBY NC pump

A

79 psig HEADER pressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is normal NC temperature

A
  • 75-105*F

- maintain <85*F for RCP bearing cooling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the makeup sources for the NC surge tank

A
  • DW

- CWHUT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the max NC flow to the LD HX

A

1500 gpm

due to vibration damage >1800gpm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How long until RCP seal damage occurs on a loss of NC

A

With Seal Injection - 10 minutes

W/out Seal Injection - 3 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What will cause NC containment isolation vlv to auto close

A

CSAS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of the 2 NC system reliefs inside of containment

A
  • 135 psig
  • ensure closure capability of NC cntmt isolations
    during a HP seal cooler leak
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What will cause an Amber light for NC pumps

A
  • STBY pump starts
  • Local start of STBY pump

any condition that causes STBY pump to run while CR HS is green flagged

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the NC pump power supplies

A

A - NBN-S01

B - NBN-S02

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What NC vlv must be operated when x-tying EW-NC

A

Close NC-99 to separate non-priority loads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What in field action is required when x-tying EW - NC

A

Throttle SDC HX outlet vlv until RCP flow alarms clear

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the cooling capacity of the PW-T mod

A
  • 2 chillers at 50%
  • Evap at 50%
  • BAC at 40%
  • 1 SFP HX
  • AS vent condenser
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What will cause the EW x-tie vlvs to AUTO close

A

Only Train A, B vlvs are manual

  • SIAS (override)
  • EW A surge tank low level 17” (no override)