What is the SSF designed to do?
Get both units to Mode 3 and hold for three days and then do a shutdown to Mode 5 with damage control measures.
What events is the SSF designed for?
Fire
Security events
Loss of all AC power
What actions must be accomplished before SSF is activated?
The SSF underground fuel storage tank is sized to operate the SSF D/G for how long?
3 days
In the “EMERG” mode of operation, which SSF D/G trips are bypassed?
Which SSF D/G trips does the Overspeed Shutdown Bypass Switch bypass?
If the Fuel Oil Solenoid Manual Override is engaged, are any SSF D/G trips active?
No, while engaged all automatic and manual D/G trips are disabled.
What are the SSF D/G trips in the “Test” mode?
What are the SSF D/G trips in the “EMERG” mode?
Where does 1SLXG get normal power from?
1TA switchgear
From the SSF, what controls are available for Primary Side Volume Control?
From the SSF, what controls are available for Primary Side Pressure Control?
Sub Bank of “D” PZR heaters
Per SLC 16.7-9 Standby Shutdown System (SSS) what is the required capacity for the sub bank of “D” Pzr heaters?
Greater than or equal to 63.5 kW measured at motor control center SMXG
Per SLC 16.7-9 Standby Shutdown System (SSS) what is the required capacity for SSF D/G fuel storage tank level?
Greater than or equal to 67 inches
From the SSF, what controls are available for Secondary Side Pressure Control?
S/G safeties
From the SSF, what controls are available for Secondary Side Volume Control?
CAPT
What S/G level at the SSF will fail open SA-5?
2 out of 4 S/G WR level less than 45%.
What are the methods for controlling S/G level at the SSF panel?
**The use of CAPT #1(2) Trip Throttle valve shall only be as a last resort. If it is used to start the pump, there is a possibility that CAPT #1(2) will overspeed.
What secondary system valves automatically close when control is transfer to the SSF?
What valves automatically open when control is transfer to the SSF?
How many Incore thermocouples are used at the SSF?
5
When must the sub bank of “D” PZR htrs be energized to ensure a PZR bubble remains in the PZR.
To limit flooding of the CAPT in the CA pump room, RN must be secured with how many minutes?
35 minutes
Per SLC 16.7-9 Standby Shutdown System (SSS) what is the required action if A required cell in a 24-Volt battery bank is < 1.36 volt on float charge?
Immediately declare the SSF nun-functional