What is the purpose of the SFP system?
To remove decay heat from spent fuel stored in the spent fuel pool.
Designed to .maintain the temperature less than 150°F with a minimum of one spent fuel cooling pump operating.
In relation to time to boil, what is the design?
The system is designed such that for a loss of cooling, the time to boil is 8 hours for ⅓ of the core off loaded and 3 hours for a full core off loaded.
What is the safety related portion of SFP?
Designed based on removing 1/3 of an infinitely irradiated core removed from the reactor within 36 hours following a reactor shutdown.
What is the capacity and power supply for the Spent Fuel Pool Cooling Pumps (P-51A/B)?
1700 gpm
MCC-7 - P-51A
MCC-8 - P-51B
What is on the shell side or tube side of the SFP Heat Exchanger?
What is its design?
Tube Side - SFP
Shell Side - CCW
Designed to withstand a temperature transient of 60°F to 212°F in 5 seconds.
What is the capacity and design of the spent fuel pool?
Reinforced concrete walls with varying thickness from 41/2 to 6 feet with a stainless steel liner.
Operational volume is 186,300 gallons.
What are the Non-Safety Related portions of the SFP system?
The Non-Safety Related function of the Spent Fuel Pool Cooling System is the filling, draining and water cleanup functions.
Spent Fuel Pool Recirc. Booster Pump
Spent Fuel Pool Demineralizer
What design features prevent water loss from the SFP?
Design features that prevent the loss of water in the Spent Fuel Pool:
What controls and indications are in the control room?
What Remote Shutdown Panel Controls, Alarms, and Indications are available?
SFP at C-40
How does SFP interact with the following systems:
Instrument Air
Component Cooling Water (CCW) System
Shutdown Cooling System
Safety Injection Refueling Water (SIRW) Tank
Fire Protection System
Primary Makeup Water (PMW)
Radwaste Systems
Station Power System
What are the PPC temperature alarms?
TIA-0925, Main Pool and TIA-0926, North Tilt Pit have a range of 50°F to 250°F and transmit to PPC points TIA_0925_D and TIA_0926_D respectively.
LO at 75°F
HI at 125°F
HI HI at 140°F
What are the SFP Temperature Limits?
Greater than 57F and less than 125F on TIA-0925 and TIA-0926 when the SFP contains irradiated fuel.
125 Limit for Demins
40F is actual min but indicator doesn’t go below 50F. So 5 degrees for margin and 2 degrees for inaccuracy gets you to 57F.
140F is SOP limit.
150F is upper design limit based on SFP Ht Exchanger inlet nozzles.
What is the Administrative minimum limit for Spent Fuel Pool boron?
Mode 1, 2, 3, 4, 5, and 6 greater than 2550 ppm
What If the Plant is in Modes 1, 2, 3, or 4, and SFP level lowers below 646’?
If the Plant is in Modes 1, 2, 3, or 4, then lowering Spent Fuel Pool level below 646’ may violate the assumptions of EA-SQG-04-01, Adjustment of Administrative Boron Concentration Limit for the Spent Fuel Pool.
What are the Spent Fuel Pool sampling requirements?
SFP shall be sampled within 24 hours prior to the start of any evolution that may change the boron concentration except for decontamination activities authorized in accordance with Attachment 2.
SFP shall be sampled in an expeditious manner after any evolution that may change the boron concentration.
How should irradiated material suspended in the SFP be handled?
Irradiated material that is temporarily suspended in the SFP should be at a lower elevation than the bottom of Door-950, SFP South Tilt Pit Gate, to prevent high radiation fields in the event of door failure.
What monitoring requirements are there for filling the SFP?
IF the Control Room TV monitor is not available to monitor SFP level, THEN a Nuclear Plant Operator, Control Room Operator, Senior Reactor Operator or a Reactor Engineering Department Engineer must be present at the SFP at all times during any SFP addition operations.
Technical Specification 3.7.14, Spent Fuel Pool Water Level
Technical Specification 3.7.14, Spent Fuel Pool Water Level
The SFP water level shall be ≥ 647 ft elevation.
APPLICABILITY: During movement of irradiated fuel assemblies in the SFP,
During movement of a fuel cask in or over the SFP.
SFP level may be below the 647 ft elevation to support fuel cask movement, if the displacement of water by the fuel cask when submerged in the SFP, would raise SFP level to ≥ 647 ft elevation.
Technical Specification 3.7.14, Spent Fuel Pool Water Level - Actions
The SFP water level shall be ≥ 647 ft elevation.
SFP water level not within limit.
Immediately
AND
SR 3.7.14.1 Spent Fuel Pool Level Surveillance
Verify the SFP water level is ≥ 647 ft elevation every 7 Days
Technical Specification 3.7.15, Spent Fuel Pool Boron Concentration
Technical Specification 3.7.15, Spent Fuel Pool Boron Concentration
The SFP boron concentration shall be ≥ 1720 ppm
APPLICABILITY: When fuel assemblies are stored in the Spent Fuel Pool.
3.7.15 Spent Fuel Pool (SFP) Boron Concentration
The SFP boron concentration shall be ≥ 1720 ppm.
SFP boron concentration not within limit.
Immediately
AND
SR 3.7.15.1 Spent Fuel Pool (SFP) Boron Concentration
The SFP boron concentration shall be ≥ 1720 ppm.
Verify the SFP boron concentration is within limit every 7 days